Thanks Ken!
1) agree since it would be more consistent. Implemented.
2) It is hard in current architecture. The good news however that I
have just added Undo/Redo for inserting tasks from RTE. Together with
selection in the Outline all just inserted from RTE tasks it is much
more useful I think. So you can type in RTE, Ctrl+Enter to parse and
add to Outline, see where in the outline your tasks are placed,  if
they are in wrong position use "Edit->Undo insert from RTE" and you
get your RTE text back and may correct it if needed and try again.

Hope that makes sense.

Andrey.

On Feb 18, 1:18 am, pottster <[email protected]> wrote:
> Hi Andrey,
>
> Thanks for all the extra functionality you are adding to the Betas.
>
> Just a couple of observations on the new parsing options for Projects/
> Folders/Tasks.
>
> Shouldn't the parsed task be added to the bottom of the list of
> siblings as happens currently with a non-parsed task?
>
> It would be useful if, in the RTE Parsing Result dialog, a destination
> column could be added to confirm the task was going to land in the
> right place.
>
> Regards,
> Ken

-- 
You received this message because you are subscribed to the Google Groups 
"MyLifeOrganized" group.
To post to this group, send email to [email protected].
To unsubscribe from this group, send email to 
[email protected].
For more options, visit this group at 
http://groups.google.com/group/mylifeorganized?hl=en.

Reply via email to