In the task properties for the Parent folder/task reduce the effort to zero.
On Mar 30, 12:23 pm, Boghdan <[email protected]> wrote: > Couldn't find the option where it would be possible to set a task to > show as 100% completed when i finish all the subtasks. E.g. when i > have a folder with 3 subtasks in it where all of them ar marked as > completed, it shows 75% in the 'Project Completion %' column next to > that folder, meaning that the folder is a task itself and should be > completed aswell. Is there any fix around it? Thanx forward -- You received this message because you are subscribed to the Google Groups "MyLifeOrganized" group. To post to this group, send email to [email protected]. To unsubscribe from this group, send email to [email protected]. For more options, visit this group at http://groups.google.com/group/mylifeorganized?hl=en.