Oops... ignore the part that says "0.255102 of a 24 hour day (so a 168 hour
week)     42.857136
how much of a                    45 hour week?"

It was part of an earlier idea I didn't edit out.



On 18 January 2011 14:15, Mary Renaud <[email protected]> wrote:

> Okay, this is explained the way someone who does not code would explain it,
> so please stick with me.
>
> Since the software already has access to the due date, lead time, and
> estimated time any task will take to complete, I was thinking it might not
> be too difficult to create a report to do the following...
>
> Take the total estimated time (using max estimated is probably best since
> it's better to plan for the worst case than the best) and divide it by the
> total amount of hours in the lead time to create some kind of "Lead Time
> Factor" (or any other more intelligent name).
>
> E.g.:
> task 1
> Estimated max: 300h
> Due date: April 3, 11:59PM
> Lead time: 98.5h (= 4d, 2h, 30min)
>      (lead time is decreased as today gets into the lead time...
>      i.e., if the start date was exactly 24 hours ago, the lead time would
> = 74.5 instead of 98.5)
> Lead time factor would be: 3.045685 (300/98.5; a number above 1.0 means
> it's physically impossible... even without sleep)
>
>
> Have a pop-up window (from the tools menu - perhaps under the heading of
> "Workload Report" or something similar) in which you can type how many work
> hours you have per day or week (whichever makes the overall coding
> easiest... I'm not a coder and may be talking gibberish, so correct for my
> lack of knowledge as necessary).
>
> Let's say it looks something like this, for argument's sake:
> " [   ]  " means entered by user
> "="        means calculated by mlo
>
> ---------------------------------------------------------------------
> Work hours per week: [ 45.0 ]
> View report for next [ 12.0 ]  week
> Starting:    [ Jan 17 ]
> {Workweek factor = 45/168 = 0.267857}
> ---------------------------------------------------------------------
>
> The software then picks out a day and time that is 12.0 weeks away and
> works backwards from there, applying the workload factor to the hours
> included in the lead time of each task and spits out totals for each week.
>
> ---------------------------------------------------------------------
> *WARNING*: Lead time for "*task 1*" too short for 45-hour workweek  {  <-
> this is determined by dividing the estimated hours of the task by the work
> hours entered above  }
>
>
> Jan 17 - Jan 23 = 0
> Jan 24 - Jan 30 = 0
> Jan 31 - Feb 6 = 0
> Feb 7 - Feb 13 = 0
> Feb 14 - Feb 20 = 0
> Feb 21 - Feb 27 = 0
> Feb 28 - Mar 6 = 0
> Mar 7 - Mar 13 = 0
> Mar 14 - Mar 20 = 0
> Mar 21 - Mar 27 = 0
> *Mar 28 - Apr 3 = 300.00 hours*
> Apr 4 - Apr 10 = 0
>
> ---------------------------------------------------------------------
>
> Let's say there's also a "task 2" with only slightly different parameters
> (a different due date and longer lead time), as well as the same "task 1":
>
> task 2
> Estimated max: 300h
> Due date: April 3, 11:59PM
> Lead time: 1176.0h (= 49d)
> Lead time factor would be: 0.255102 (300/1176)
>
> 0.255102 of a 24 hour day (so a 168 hour week)     42.857136
> how much of a                    45 hour week?
>
>
> So now the Workload summary (which includes all/both tasks) would look like
> this:
>
> Work hours per week: [ 45.0 ]
> View report for next [ 12.0 ]  week
> Starting:    [ Jan 17 ]
> {Workweek factor = 45/168 = 0.267857}
>
>
> ---------------------------------------------------------------------
> *WARNING*: Lead time for "*task 1*" too short for 45 hour workweek  (  <-
> this is determined by dividing the estimated hours of the task by the work
> hours entered above  )
>
>
> Jan 17 - Jan 23 = 0
> Jan 24 - Jan 30 = 0
> Jan 31 - Feb 6 = 0
> Feb 7 - Feb 13 = 0
> Feb 14 - Feb 20 = 42.86   {See workload hours calc explanation below}
> Feb 21 - Feb 27 = 42.86
> Feb 28 - Mar 6 = 42.86
> Mar 7 - Mar 13 = 42.86
> Mar 14 - Mar 20 = 42.86
> Mar 21 - Mar 27 = 42.86
> *Mar 28 - Apr 3 = 342.86 hours*
> Apr 4 - Apr 10 = 0
>
> ---------------------------------------------------------------------
>
> Workload hours calc explanation:  Sum of [for each task: (Lead time factor
> / Workweek factor * work hours = 42.86)]
>
>
> So, now you can scroll down your list of upcoming weeks and see if there
> are any in which the workload is above your working hours. (Even better if
> the window bolds the font for any week where the total workload hour > work
> hours per week.) Then you just have to go to tasks in and around that week's
> range and fiddle with the lead times, deadlines, etc. and then come back and
> check to see if your workload is good enough to prevent bottlenecks.
>
> (Note, laid out this way, my idea would require keeping a separate file for
> home and work so that home tasks don't count in time for work tasks...
> but... SO? I would GLADLY maintain a separate work file in order to balance
> my work deadlines.)
>
>
> I can think of other little tweaks that would make this even better but
> this is the most bare-bones approach I can come up with that would REALLY
> REALLY help boost MLO's time management functionality.
>
> Did that make sense to ANYONE?
>
> What do you all think? Would this be enough to cover, at least for now, the
> workload issues some people are having?
>
> Andrey (hope you don't mind me calling you by your first name): Is this as
> easy to implement as I suspect or are there complications I haven't thought
> of?
>
> Sorry for the long post... again! :)
> Mary
>

-- 
You received this message because you are subscribed to the Google Groups 
"MyLifeOrganized" group.
To post to this group, send email to [email protected].
To unsubscribe from this group, send email to 
[email protected].
For more options, visit this group at 
http://groups.google.com/group/mylifeorganized?hl=en.

Reply via email to