i just created a few items, within certiain folder tasks

then later i just applied the due dates to 2 of them
one task had due date in 2 days, and another in 21 days

i did not change the view in todo tab - so it was Active Actions
and i also did not change the sorting either - so it is Computed Score
Descending

but these items with due dates appear at the end of the Active Actions
view

i have shared the images, and the mlo file here
http://www.mediafire.com/?ue60avsunyrn9b8


On Jan 31, 6:01 am, Lisa Stroyan <[email protected]> wrote:
> What View or sorting Criteria are you using (off to the left, after
> Advanced)?
>
> Lisa
>
> On Mon, Jan 30, 2012 at 9:55 AM, vikram.sjn <[email protected]> wrote:
> > hi
> > i am using mlo after some time now
>
> > i notice that the tasks which have due date set, but not start date,
> > these are appearing at the end of the todo list
>
> > i am using 3.6.1
>
> > and have only few tasks, and just two have due dates set
> > the ones with due dates are appearing at the end of todo list
>
> > is this correct ?
> > i was expecting the ones with due dates to appear at the top
>
> > vikram
>
> > --
> > You received this message because you are subscribed to the Google Groups
> > "MyLifeOrganized" group.
> > To post to this group, send email to [email protected].
> > To unsubscribe from this group, send email to
> > [email protected].
> > For more options, visit this group at
> >http://groups.google.com/group/mylifeorganized?hl=en.
>
> --
> Lisa
>
> ------------------------------
> Lisa Stroyan, mailto: [email protected] <[email protected]>

-- 
You received this message because you are subscribed to the Google Groups 
"MyLifeOrganized" group.
To post to this group, send email to [email protected].
To unsubscribe from this group, send email to 
[email protected].
For more options, visit this group at 
http://groups.google.com/group/mylifeorganized?hl=en.