Hi,

thanks much. Also for your screenshot.

i have purchased so many apps and wasted money due to lack of manuals.
hence, i am reaching out like this i hope you understand.

i would appreciate if you could ans the following

1. does the app allow us to specify a project calendar ie days of week and
what hrs can be worked on this project. if not does it at least let us
specify how many hours we are working on a
project per week ?

2. how does task scheduling work ? can we supply the effort estimates and
does teh app populate the start and end dates ?

3. the project % complete does it consider the effort estimates ? ie if 3
tasks are there with effort estimates of 100h, 50h, 50h then
 does the project reflect a total of 200h of effort. subsequently if the
100h task gets completed then what % does the project report
got completed ?

thanks again for the help. appreciate it deeply.
regards,
MD



thanks so much for your time.
regards
MD

On Wed, May 30, 2012 at 1:33 PM, EyeBurn <[email protected]> wrote:

> MD,
>
> I just sent you an email with a screencap of the "Task Details" using
> my iPad app.
>
> 1.
> (description of task/task title)
> Contexts ->
> Start: None ->
> Due: None ->
> Reminder ->
> Recurrence ->
> Notes ->
> Importance: Normal ->
> Urgency: Normal ->
> Goal ->
> Folder (toggle switch)
> Hid Branch in To-Do (toggle switch)
> Subtasks in Order (toggle switch)
> Project ->
> Effort: Normal ->
> Time Required ->
> Parent: <Inbox> ->
> Share via email (tapable link)
> (date the task was added)
> (date the task was last changed)
>
> 2. yes
>
> 3. I have my set to whatever the default is (The Project completion
> status bar appears to progress simply as I mark tasks complete)
>
> 4. I user a very hierarchical method and also enable "Complete
> subtasks in order". View "Active by Project" appears like a cascading
> tree, but only lists the highest level task. Once I complete said
> task
> per project that task will go away and the next task shows up (per
> project).
>
> 5. I have an idea how dependency works (with MLO), but I haven't
> confirmed it...so I'll leave this to someone else to reply.
>
> thx,
>
> Ben
> Houston, TX
>
> On May 30, 4:50 am, MD <[email protected]> wrote:
> > Hi,
> >
> > i am thinking about purchasing this app and would appreciate it if
> > someone who owns the app can answer these questions
> >
> > 1. In task properties whats fields do you have under 'more details'
> > 2. Is there effort estimate, actual effort and percent complete for
> > tasks and projects (as summary task)
> > 3. How do you calculate the percent complete or the green line length
> > for projects ?
> > 4. How does the list look like under 'Active by project', is it like a
> > next action list ie one action per project ? If so then what happens
> > in dependency situation say one task in one project is dependent on
> > the completion of another task in another project ?
> > 5. Could someone explain how dependency works can we setup a start to
> > finish etc kind of dependency or is it tasks have to be done in order
> > under a project folder ?
> >
> > thanks much.
> > MD
>
> --
> You received this message because you are subscribed to the Google Groups
> "MyLifeOrganized" group.
> To post to this group, send email to [email protected].
> To unsubscribe from this group, send email to
> [email protected].
> For more options, visit this group at
> http://groups.google.com/group/mylifeorganized?hl=en.
>
>

-- 
You received this message because you are subscribed to the Google Groups 
"MyLifeOrganized" group.
To post to this group, send email to [email protected].
To unsubscribe from this group, send email to 
[email protected].
For more options, visit this group at 
http://groups.google.com/group/mylifeorganized?hl=en.

Reply via email to