Hello,

One would expect that the Review Status of a task gets synchronized via the 
case. Andrey confirmed that it should work. But it doesn't work for me (and 
for a colleague also using the latest MLO)

Note: these tests were performed with the latest production release 4.0.0 
on the two PCs

First test:
On PC A, I use an existing task where I have setup the review properties: 
next review is ticked and date is set, review frequency is 1 week and the 
last review date is set.
This review setting is not set on PC B. As recommended I changed the name 
of the task (by a letter) and changed the urgency.
After sync, on PC B, the name is changed, the urgency is changed but the 
review property is still empty.

Second test:
Same test but with a completely new task. Everything is created on PC B 
except for the review settings.

Configuration:
On both pc's the advanced sync parameters are set to bidirectional and none 
of the "do not..." is selected.

Jmm

-- 
You received this message because you are subscribed to the Google Groups 
"MyLifeOrganized" group.
To unsubscribe from this group and stop receiving emails from it, send an email 
to [email protected].
To post to this group, send email to [email protected].
Visit this group at http://groups.google.com/group/mylifeorganized?hl=en.
For more options, visit https://groups.google.com/groups/opt_out.


Reply via email to