Thanks for the reply. I describe the problem. I have a task with an end date. To accomplish this task are some tasks to complete before. As an example, 10 weeks before the end date must be ordered something. Now changes the end date must be manually changed all the sub task. Lead time for inherited parent dates would be a solution. Any other ideas?
-- You received this message because you are subscribed to the Google Groups "MyLifeOrganized" group. To unsubscribe from this group and stop receiving emails from it, send an email to [email protected]. To post to this group, send email to [email protected]. Visit this group at http://groups.google.com/group/mylifeorganized. To view this discussion on the web visit https://groups.google.com/d/msgid/mylifeorganized/304a9044-9ab5-4696-9dd4-388832c82f4d%40googlegroups.com. For more options, visit https://groups.google.com/groups/opt_out.