I'm not sure if I have the following scenario implemented properly: 25 times a month, I need to perform a task. I can perform the task on any days and however many times on a given day as long as I complete it 25 times each month.
Here is how I have it implemented: I have a project set up to recur on the 1st of each month. The project has 25 identical tasks. Problem: Each time I mark the project as complete, all of its subtasks are deleted. There are some months when I do not complete this task a total of 25 times and I would like to be able to reference this information. -- You received this message because you are subscribed to the Google Groups "MyLifeOrganized" group. To unsubscribe from this group and stop receiving emails from it, send an email to [email protected]. To post to this group, send email to [email protected]. Visit this group at http://groups.google.com/group/mylifeorganized. To view this discussion on the web visit https://groups.google.com/d/msgid/mylifeorganized/d106a0de-6bcb-464f-a10c-503be89eedd4%40googlegroups.com. For more options, visit https://groups.google.com/groups/opt_out.