No this is not currently possible. I agree it would be useful at times, because you end up having to manually adjust the dates.
On Thursday, 28 May 2015 04:27:27 UTC-6, Ryan Sheftel wrote: > > Is it possible to link the start date of a task to the due date of a task > it depends on. That way if I update the due date of a task, say it took > longer than originally planned, then the start date (and due date if the > lock period is checked) of all dependent tasks would adjust accordingly. > > This would be very helpful in using MLO for project planning. thanks. > -- You received this message because you are subscribed to the Google Groups "MyLifeOrganized" group. To unsubscribe from this group and stop receiving emails from it, send an email to [email protected]. To post to this group, send email to [email protected]. Visit this group at http://groups.google.com/group/mylifeorganized. To view this discussion on the web visit https://groups.google.com/d/msgid/mylifeorganized/851fe20f-c304-41e1-941f-fd5f7ff86f00%40googlegroups.com. For more options, visit https://groups.google.com/d/optout.