OK, we discussed this a few months ago but I don't think you were ready yet for that discussion.

Short answer: no, you cannot make a single view with the contents you want using MLO as currently implemented.

Long answer:
There are a lot of "standard" filters including Actions, Hierarchy, Completed, Text, Contexts, Flags, Start date and References. For the most part these are on or off, or involve a simple, one-dimensional set of choices. If you cannot accomplish what you want using these filters you can use the Advanced filters where you get to build complex tests with logical operations like OR AND & NOT, parentheses, and so on.

The filters you called Standard are probably the Action filters, with values All, Available, NextActions and Completed. These filters are very useful, covering the most commonly used subsets of task status. From time to time you need something that does not quite match up with the standard values, and then you need to go to the Advanced Filters to build exactly what you want. And here is the problem: There should be an advanced filter IsNextAction, but there isn't. You can only get next actions using the Actions filter, which does not allow for logical operations like OR. So you cannot build a view for Next Actions OR tasks not in a project. On the other hand, if it would help you, you can certainly build a view for next actions and a view for tasks not in a project, and display the two views side by side, or top over bottom.

So, your choices are
1. Request the implementation of an IsNextAction advanced filter and wait for it to be implemented 2. on a mobile device, create a half-screen widget for a Next Actions view and a half-screen widget for tasks not in a project and display them together on a single screen. 3. on Windows, create two workspaces, one locked to a Next Actions view and the other locked to a tasks-not-in-a-project view. In tools>options>Behaviour turn on Allow Multiple Instances. Open two copies of MLO. In one, open the Next Actions workspace and in the other open the task-not-project workspace. Arrange the two windows on a single screen.

On 4/1/2016 7:25 AM, J Smith wrote:
UPDATE

Okay after spending time on experimentation, I think I have now worked out what each of the standard filters does.

But I can't work out how to create a view that just show Next Actions and tasks that are not part of a Project.

i.e. I am trying to compress the full complexity of complex project but at the same time not hide individual tasks that are not part of any formal project.

Any suggestions?

J


On Friday, 1 April 2016 11:14:42 UTC+1, J Smith wrote:

    Hello

    I am just revisiting how MLO task filtering works at core.

    To be honest I am finding it extremely hard to get my head around
    the exact distinctions between:
    - Active
    - Available
    - Complete Tasks in Order
    - Next Action

    When I first joined MLO 18 months ago I found the help files to be
    too hard to understand and I eventually only got there only by
    experiment!
    And now 18 months later I've rather forgotten the distinctions.

    To save me (and anyone new) the time, has anyone done any good
    explainer videos yet?

    Many thanks

    J


    PS. Fwiw, I want to create a view that shows all my Next Actions
    of formal MLO Projects _and_ any Tasks that are not part of any
    Project.
    i.e. It needs show tasks that are not part of a Project but hide
    any tasks that are part of MLO Projects which are not the NEXT
    Action.
    Also I want to hide tasks by putting them into the future (e.g.
    using Start Date).

    But I am now trying work out if there is a standard view that
    already does this... !










--
You received this message because you are subscribed to the Google Groups "MyLifeOrganized" group. To unsubscribe from this group and stop receiving emails from it, send an email to [email protected] <mailto:[email protected]>. To post to this group, send email to [email protected] <mailto:[email protected]>.
Visit this group at https://groups.google.com/group/mylifeorganized.
To view this discussion on the web visit https://groups.google.com/d/msgid/mylifeorganized/811a7b6b-b982-4faf-95a8-80086a0463b5%40googlegroups.com <https://groups.google.com/d/msgid/mylifeorganized/811a7b6b-b982-4faf-95a8-80086a0463b5%40googlegroups.com?utm_medium=email&utm_source=footer>.
For more options, visit https://groups.google.com/d/optout.

--
You received this message because you are subscribed to the Google Groups 
"MyLifeOrganized" group.
To unsubscribe from this group and stop receiving emails from it, send an email 
to [email protected].
To post to this group, send email to [email protected].
Visit this group at https://groups.google.com/group/mylifeorganized.
To view this discussion on the web visit 
https://groups.google.com/d/msgid/mylifeorganized/56FE98B6.60109%40dwightarthur.us.
For more options, visit https://groups.google.com/d/optout.

Reply via email to