Christoph:

There's a little box called "Lock Period" just below Due Date & Lead Time. 
Uncheck this box and the dates are independent.

Ed Comerford

-----Original Message-----
From: [email protected] <[email protected]> On 
Behalf Of Christoph Zwerschke
Sent: Wednesday, December 4, 2019 1:34 AM
To: [email protected]
Subject: Re: [MLO] Start Date & Due date are locked together: Both change 
simultaneously


Am 03.12.2019 um 19:39 schrieb Ed Comerford:
> I suddenly have a situation where the Start Date and Due Date seem to 
> be locked. If I change one, the other changes. I can't have different 
> dates in the 2 fields.
You probably have "lock period" checked.

-- Christoph

--
You received this message because you are subscribed to the Google Groups 
"MyLifeOrganized" group.
To unsubscribe from this group and stop receiving emails from it, send an email 
to [email protected].
To view this discussion on the web visit 
https://groups.google.com/d/msgid/mylifeorganized/c712c196-ce17-d14a-7bc3-47c915c36969%40online.de.

-- 
You received this message because you are subscribed to the Google Groups 
"MyLifeOrganized" group.
To unsubscribe from this group and stop receiving emails from it, send an email 
to [email protected].
To view this discussion on the web visit 
https://groups.google.com/d/msgid/mylifeorganized/008201d5aba3%24f87d5540%24e977ffc0%24%40shaw.ca.

Reply via email to