Yes leave "Complete subtasks in order" UNCHECKED.  Then use the 
Dependencies farther down that pane.  Add the task that has to be completed 
before this one becomes active.  It gives a lot more flexibility.  For 
Example Task A and B are both active so have no dependencies.  Task C will 
be active when both A and B are done so it has the Dependencies of Task A 
and B OR Task C is active when Task A is complete thus only has Task A as a 
dependency.
Susannah

On Thursday, October 22, 2020 at 4:41:22 AM UTC-4 Grant wrote:

> I have a few projects where I have set the 'complete tasks in order' 
> enabled.  This works for the core plan, but often I run into something 
> small I need to do in addition to the Next Task on a particular day for the 
> project.  Thus I want both to show on my active tasks view.  Is there a way 
> to do this with a setting, etc (rather than a work around like two sub 
> project folders, etc)?
>
> Thanks
> Grant
>

-- 
You received this message because you are subscribed to the Google Groups 
"MyLifeOrganized" group.
To unsubscribe from this group and stop receiving emails from it, send an email 
to [email protected].
To view this discussion on the web visit 
https://groups.google.com/d/msgid/mylifeorganized/2d50014e-b03e-4dd0-8213-251119587f9fn%40googlegroups.com.

Reply via email to