Yes leave "Complete subtasks in order" UNCHECKED. Then use the Dependencies farther down that pane. Add the task that has to be completed before this one becomes active. It gives a lot more flexibility. For Example Task A and B are both active so have no dependencies. Task C will be active when both A and B are done so it has the Dependencies of Task A and B OR Task C is active when Task A is complete thus only has Task A as a dependency. Susannah
On Thursday, October 22, 2020 at 4:41:22 AM UTC-4 Grant wrote: > I have a few projects where I have set the 'complete tasks in order' > enabled. This works for the core plan, but often I run into something > small I need to do in addition to the Next Task on a particular day for the > project. Thus I want both to show on my active tasks view. Is there a way > to do this with a setting, etc (rather than a work around like two sub > project folders, etc)? > > Thanks > Grant > -- You received this message because you are subscribed to the Google Groups "MyLifeOrganized" group. To unsubscribe from this group and stop receiving emails from it, send an email to [email protected]. To view this discussion on the web visit https://groups.google.com/d/msgid/mylifeorganized/2d50014e-b03e-4dd0-8213-251119587f9fn%40googlegroups.com.