On Mon, 18 Aug 2003 [EMAIL PROTECTED] wrote:

> The reason for that is that if one does not call call before dig, one would
> be liable. If one does call and misunderstands, the survey company would be
> liable. So those companies prefer to leave very clear marks.

The way it works in California is that the digger marks the work area
in white paint and submits the location to the USA hotline.  The hotline
distributes this to all of the utilities, which then mark the location of
their underground facilities, color coded (Blue - water, Red - power,
Orange - telco/cable, Yellow - gas).  The digger must will take care not
to damage anything marked.

http://www.digalert.org/

-- 
Jay Hennigan - CCIE #7880 - Network Administration - [EMAIL PROTECTED]
WestNet:  Connecting you to the planet.  805 884-6323      WB6RDV
NetLojix Communications, Inc.  -  http://www.netlojix.com/