And now:Ish <[EMAIL PROTECTED]> writes:
Finding a Number the Feds Can Live
With
http://www.y2ktimebomb.com/Washington/Congress/creg9909.htm
By Charlie Register
March 2, 1999
Some U.S. Agencies Redefine Mission Critical to
Make Y2K Deadline
As with all large reports, it takes time for the press to go
through the pages and highlight the salient points to
report. In
their haste to get something to make a timely report, reporters
too often rely on report summarization's to make their first
deadline. Summaries by design gloss over details, however,
and we all know where the devil lies. So with that in mind,
let's consider the details of Congressman's Horn's quarterly
Y2K Federal Report Card.
Congressman Stephen Horn, the government's exam giver
when it comes to Year 2000 readiness, issued his latest
"Year 2000 Report Card" recently and reluctantly gave the
Federal Government a "C+" for its computer renovation
efforts, an improvement from the previous "D" grades given in
November and August of last year.
Horn (R-CA), a former college professor, was clearly unhappy
with the progress report. While saying that the looming Year
2000 deadline had awakened many agencies had "into a
frenzied burst of activity," clearly some large and vital
agencies were still lagging in their Y2K remediation efforts.
"Six organizations lowered an otherwise stellar grade to
mediocrity," Horn said in a statement along with the first
government report card of 1999, and seventh overall. "Put
together, these agencies - the Departments of Agriculture,
Defense, Health and Human Services, State and
Transportation, and the Agency for International Development
- are responsible for more than 50 percent of all
mission-critical systems in the Federal government. Our
concerns about these agencies are plentiful."
Still, compiled results from Federal departments and agencies
showed a remarkable increase in the number of agencies
receiving "A" grades, up from three in the previous November
1998 report to eleven in the February 1999 report.
"Many agencies have made truly remarkable progress in
bringing their mission-critical computer systems into Year
2000 compliance," Horn said in light of the newly released
figures.
A closer look at the numbers shows that as of February 12,
government agencies in total reported 79% of 6404 mission
critical systems ready to go for Y2K. That's up from 61%
readiness reported in November 1998.
But wait. That was 61% of 6,696 systems deemed vital in
November for the continuity of the U.S. government through
the date change. Clearly that's a distinction worth noting. Or
is it?
The number of mission critical systems has dwindled since
May of last year from 7,336 to 6,404, according to the last
four report cards from Congressman Horn's Subcommittee of
Government Management, Information and Technology. That
represents almost a 13% reduction in the number of vital
systems. Should we be surprised by this? Not hardly.
Many Y2K analysts predicted as the Year 2000 deadline
loomed larger in the window, agencies falling behind the
remediation curve would start redefining down the number of
systems needed to keep their agency operating. Major cuts in
systems would leave agencies crippled come the new year,
analysts predicted. And since remediation at the government
level was late in starting and slow in progressing, there would
be no choice but to engage in the "Y2K Limbo" to make the
federally mandated March 31, 1999 deadline. So in other
words, agencies were going to have to determine the
minimum number of systems they could "live with."
The Department of Defense has been the pack leader in this
austerity program, registering 2,306 vital systems now as
opposed to 2,803 in May of last year, a drop of 497 systems.
This represents almost half of the overall computer systems
adjustment from 7,336 to 6,404 (932).
But it's the Department of Agriculture that presents the most
confusing array of figures. The USDA trimmed its mission
critical systems from 1,080 in May 1998 to 353 by February
1999. Along the way they had completed work on 407 of 647
vital systems by August of 1998 and 235 of 362 mission
critical systems by November 1998. As of February, 268 of
353 systems classified as priority were Y2K ready. On the
surface it appears the agency is going backwards, but
obviously many now less important systems will be Y2K
ready come the date change.
The ranking of computer systems poses the interesting
dilemma of establishing just what is vital to the continuity of
each agency. Early on when standards for determining
important systems were less clear, agencies like the Veteran
Administration grossly underestimated what was important to
stay in operation. The VA's great awakening to the immensity
of the Y2K Problem came when they reported a revised 319
systems in their August 1998 figures, up from just 11 mission
critical systems tallied three months earlier.
Interestingly, Horn's report card for that period indicated
that
64% of the previously mentioned 11 systems were slated to
be compliant by the March 1999 deadline. But in the next
quarterly report, 61% of the newly revised 319 figure were
already renovated for Y2K. That represents 194 fixed
systems that were previously understood as not necessary to
keep the agency functioning.
A close look at the numbers shows that not all agencies
embraced a draw down in critical systems in order to make
the federal deadline. In addition to the Veteran's
Administration's upward adjustment, the Department of
Justice continues to adjust its systems higher, increasing the
number from 197 to 221 over the last nine months. The
Department of Energy, which Congressman Horn noted in his
statement as making significant progress in the last three
months, has increased its total needed systems by nine to
420.
Other agencies not finished with their remediation work have
resisted making major concessions as of yet. The
Departments of Interior, FEMA, and NASA have shaved just
one system in nine months while the Treasury Department
has cut their number by just two.
From the latest report, it's clear that the Defense,
Transportation and Agriculture Departments are the agencies
saddled with the greatest challenges. Congressman Horn's
report estimates that by the March 1999 deadline, 87% of the
USDA's systems will be ready and 82% of the DOD
computers will be renovated. Another key agency to watch is
the Treasury Department, which is projected to have 95%
ready by the end of March.
Arguably these are four of the most vital agencies to the
security of U.S. citizens and they will need to engage in some
heavy duty contingency planning to fill in the gaps should
some computers fail to function effectively when Year 2000
dates start entering their systems.
But the oddest and possibly most disturbing statistics in the
report center around the Agency for International
Development. With just seven computer systems in need of
fixing for the date change, the AID in May 1998 calculated
that 17%, or one system, would be ready for the Federal
deadline. By November, the AID reported 14% of its
renovations complete. Congressman Horn projected that at
that pace, AID would be compliant by 2023.
As of February 1999, the agency reports zero percent of its
systems now compliant and Horn now projects their
completion date as "unknown." Evidently, they could not find
a number they could "live with."
&&&&&&&&&&&&&&&&&&&&&&&&&&
Tsonkwadiyonrat (We are ONE Spirit)