Hi Carlton,

> You both took a guess at how long a task you hadn't done would
> take, and you came up with different guesses.  How does
> dishonesty enter into it?

I think that what Carlton interpreted as dishonest was all of the 
rounding upward.  The folks rounded up each of the individual 
subtask estimates before adding them together, then rounded that 
total upward (from 8 days to 10) to arrive at the task estimate.

That could be dishonesty.  It could also be risk management, and 
wanting to produce an estimate that they had high confidence they 
could meet.  Perhaps the original subtask estimates were made 
with the assumption that things would go reasonably well.  Maybe 
rounding each of those upward accounts for possible snags.  And 
maybe rounding the total upward accounts for coordination and 
integration issues.

Dale

-- 
Dale Emery, Consultant
Collaborative Leadership for Software People
Web:    http://www.dhemery.com
Weblog: http://www.dhemery.com/cwd

Truth is always subversive. --Anne Lamott


To Post a message, send it to:   [EMAIL PROTECTED]

To Unsubscribe, send a blank message to: [EMAIL PROTECTED]

ad-free courtesy of objectmentor.com 
Yahoo! Groups Links

<*> To visit your group on the web, go to:
    http://groups.yahoo.com/group/extremeprogramming/

<*> To unsubscribe from this group, send an email to:
    [EMAIL PROTECTED]

<*> Your use of Yahoo! Groups is subject to:
    http://docs.yahoo.com/info/terms/
 



Reply via email to