LAX people mover to begin reliability testing as dispute between city and
contractor heats up
[image: A large concrete bridge arching over a paved street on a clear,
sunny day. A palm tree is in the forefront on the right, and a large pillar
is on the left.]
If you catch yourself at the airport once system demonstration begins, you
will see empty People Mover cars traversing the 2.2-mile tracks on the same
schedule the train will use when it opens.
(
Courtesy of Los Angeles World Airports and LAX Integrated Express Solutions
)

This story is free to read because readers choose to support LAist. If you
find value in independent local reporting, make a donation to power our
newsroom today
<https://support.laist.com/quick-donate?ms=prenote&utm_source=laist&utm_medium=onsite_prenote&utm_campaign=prenote&utm_content=control_v1>
.

The contractor building the LAX Automated People Mover will soon initiate a
simulation of how the train will operate when it begins shuttling travelers
between airport terminals and the L.A. Metro system.

If you catch yourself at the airport once this phase of testing begins the
week of April 20, you'll see empty cars traversing the 2.25-mile-long
tracks on the same 24/7 schedule the train will use when it opens.

“It’s a big milestone for the project, and a visible milestone,” said Jake
Adams, an airport executive who is overseeing $5.5 billion in LAX upgrades,
including the people mover.

Meanwhile, Los Angeles World Airports, the city agency that manages LAX,
and its contractor for the people mover have escalated their rhetoric over
a dispute that began last year
<https://laist.com/transportation/lax-people-mover-delay> over faulty
electrical equipment, according to an LAist review of correspondences
received through a public records request.
Keep up with LAist.
If you're enjoying this article, you'll love our daily newsletter, The LA
Report. Each weekday, catch up on the 5 most pressing stories to start your
morning in 3 minutes or less.
Subscribe

Adams said he’s “fairly optimistic” that the dispute can be resolved
separately from opening the train to the public, even if it intensifies
into a legal battle.

Considering the projected timeline for this next phase of testing, the
train likely won’t be open in time for the World Cup in June, which was once
slated to open in 2023.
<https://laist.com/news/transportation/lax-people-mover-delay-grand-jury-report>

Adams said the airport’s peak summer traveler count “far exceeds” the
number of people expected for the World Cup and that he doesn’t anticipate
any issues.
Do you know something about the Automated People Mover that LAist should
look into?

If you have a tip, you can reach me on Signal. My username is kharjai.61.

   - You can follow this link
   
<https://signal.me/#eu/jYSBvrbojVkW-siQijoNE0SZaa47ws06Fib4W4H3ExVqKafQBzFKlJKcq2niBV95>
to
   reach me there or type my username in the search bar after starting a new
   chat.
   - For instructions on getting started with Signal, see the app's support
   page.
   
<https://support.signal.org/hc/en-us/categories/5592576449306-Getting-Started>
   - And if you're comfortable just reaching out by email I'm at
   [email protected].

Testing the reliability of the train

The testing milestone that is slated to begin the week of April 20 is
designed to assess the reliability of the train.

“The requirement is that [the contractor has] to operate it for 30
consecutive days without a hiccup,” Adams said of the testing phase known
as “system demonstration.”

What a “hiccup” could look like ranges, Adams said. An example of a major
issue that could restart that 30-day clock is if one of the train cars
breaks down. A more minor one would be if a train door fails to open at a
platform.

Adams said the process is likely to take a total of 60 days based on
conversations with other airports that have developed similar people mover
systems.
Trending on LAist

   - [image: People hold handmade signs above their heads reading "We are
   Students" and "ICE out of funding."]
   
<https://laist.com/news/education/la-unified-school-district-reaches-tentative-labor-deal-with-teachers>
   LAUSD reaches labor deals with teachers, principals. Why schools could
   still be closed Tuesday
   
<https://laist.com/news/education/la-unified-school-district-reaches-tentative-labor-deal-with-teachers>
   - [image: A group of people with varying skin tones hold up signs that
   say "Parents Support Educators!" "LAUSD Settle a fair contract now!" and
   "Fair Pay Fair Contract."]
   
<https://laist.com/news/education/lausd-strike-april-2026-strike-update-union-negotiations-faq>
   This week's LAUSD strike could close schools indefinitely. Here's what
   to know
   
<https://laist.com/news/education/lausd-strike-april-2026-strike-update-union-negotiations-faq>
   - [image: Closeup of a large turtle swimming in a an aquarium tank. The
   floor and walls of the tank are painted turquoise blue.]
   
<https://laist.com/news/aquarium-of-the-pacific-needs-help-with-an-enormous-rescued-sea-turtle>
   Aquarium of the Pacific needs help with an enormous rescued sea turtle
   
<https://laist.com/news/aquarium-of-the-pacific-needs-help-with-an-enormous-rescued-sea-turtle>

Contractual dispute over electrical maintenance remains open

In November, LAist reported on a dispute over repairs to equipment in a
metering cabinet. That work required power to be partially shut down
between February and July 2025, temporarily delaying critical testing of
the technology that allows for central control of the people mover’s
systems.

Though the technical issue has been resolved, the contractual dispute
remains open. LINXS, the group of companies contracted to design, build and
operate the train, has taken the position that the repair work isn’t
included in its scope of work. Los Angeles World Airports disagrees.

As of October, LINXS said the extra work cost $36 million, according to a
document detailing LINXS’ claim that LAist received through a public
records request.

The contractor group in December filed a claim under a section of state law
that governs complaints against public entities. The L.A. City Attorney's
Office rejected the claim in January, initiating a six-month window within
which LINXS can sue the city.

“We will not comment on active disputes,” a spokesperson for LINXS said in
an email when LAist reached out about the issue last month.

In January 2026, when there was concern that the technical issue with the
metering cabinet was reoccurring, LAX officials directed LINXS to
investigate the issue. The contractor group initially refused to do so.

William Dachs, CEO of LINXS, said in a letter to the city in January that
“failure to resolve this … will ultimately lead to contract termination
this coming fall, resulting in the City of Los Angeles having to repay the
Lenders’ Liabilities which, at this early stage, is estimated to be over
$1.1 Billion.”
Who is LINXS?

LINXS stands for LAX Integrated Express Solutions. It is the name of the
group that formed in 2018 to design, build and operate the Automated People
Mover. It’s made up of four large engineering and construction companies:
Fluor, Balfour Beatty Infrastructure, Flatiron West and Dragados.

Ultimately, a joint investigation found the concerns about the reoccurring
issues were unfounded. Still, the episode reflects how uniquely contentious
the dispute is.

Whereas past disputes between LINXS and the airport were resolved through
settlements that have so far totaled hundreds of millions of dollars and
resulted in schedule extensions, the dispute over maintaining electrical
equipment is the one that has gotten closest to potential litigation.

“Other relief events that we’ve dealt with up to this point … we could
agree there were some things that were not totally within LINXS’ control,”
Adams said. “This relief event is very different. We believe there is
absolutely no merit to this claim.”

Disputes between LINXS and two of its subcontractors have already resulted
in litigation,  <https://laist.com/transportation/lax-people-mover-linxs>with
one subcontractor accusing LINXS of “secretive, deceptive and improper
conduct” and neglecting to pass settlement money down to subcontractors.

An L.A. County Civil Grand Jury report released last year claimed that
LINXS has used the dispute resolution process and “political pressures,”
such as L.A.’s status as host city for several upcoming mega-events, to
force contract extensions and additional compensation
<https://laist.com/news/transportation/lax-people-mover-delay-grand-jury-report>throughout
the design and construction process.
More LAist watchdog reporting

   - [image: A U.S. Department of Homeland Security sign is displayed at
   the U.S. Customs and Border Protection headquarters on May 18 in
   Washington, D.C.]
   
<https://laist.com/news/federal-judge-orders-trump-administration-to-stop-coercing-immigrant-children-to-self-deport>
   Federal judge orders Trump administration to stop coercing immigrant
   children to self-deport
   
<https://laist.com/news/federal-judge-orders-trump-administration-to-stop-coercing-immigrant-children-to-self-deport>
   - [image: An orange bus with advertisements and a white sign that reads
   "Metro Local" passes by a large gray building.]
   <https://laist.com/transportation/trump-budget-2028-olympics-metro>
   President Trump's budget request doesn't include $2 billion for Metro's
   2028 Olympics plan
   <https://laist.com/transportation/trump-budget-2028-olympics-metro>
   - [image: sdfjlksjfkl]
   <https://laist.com/transportation/west-hollywood-rail-metro>
   WeHo rail extension route approved (mostly) with assurances there won’t
   be any delays
   <https://laist.com/transportation/west-hollywood-rail-metro>

What happens next? Is there a date for opening?

There are still a few more steps to complete once the system demonstration
is successful, including resolving a dispute involving damage to the
sprinkler systems that water plants along roads near the airport. Those
roads received new landscaping as part of the project.

“LINXS is taking a very contractual position that they have to complete all
of the work that's in their contract before they can open the train,” Adams
said. “We are taking the position that the irrigation absolutely has
nothing to do with operating the train.”

Adams characterized the conversations to “decouple” the sprinklers from the
actual train itself as “active.”

The final steps include getting approval from the California Public
Utilities Commission and testing the train with volunteers.

Adams did not commit to a date for when travelers will be able to fully use
the train.
You come to LAist because you want independent reporting and trustworthy
local information. Our newsroom doesn’t answer to shareholders looking to
turn a profit. Instead, we answer to you and our connected community. We
are free to tell the full truth, to hold power to account without fear or
favor, and to follow facts wherever they lead. Our only loyalty is to our
audiences and our mission: to inform, engage, and strengthen our community.

Right now, LAist has lost $1.7M in annual funding due to Congress clawing
back money already approved. The support we receive from readers like you
will determine how fully our newsroom can continue informing, serving, and
strengthening Southern California.

If this story helped you today, please become a monthly member today to
help sustain this mission. It just takes 1 minute to donate below.

Your tax-deductible donation keeps LAist independent and accessible to
everyone.
--------------------------------------------------------------
You are receiving Jack Keady's American Airlines Aviation News


* To UNSUBSCRIBE from this list at any time, OR make changes to your 
subscription, please visit:
  http://keady.news/info

* You may reach Jack Keady at:
  [email protected]

* View the LIST ARCHIVE at:
  http://keady.news/archive

Reply via email to