Yashwant Dhakad commented on OFBIZ-13261:
-----------------------------------------

*Steps to Reproduce and Code Fix Summary*

*Issue Description*

When an exception day is set in the calendar, it is not honored during 
production run scheduling. As a result, the system calculates the completion 
date incorrectly by including the exception day.

*Steps to Reproduce the Issue*
 #  *Calendar Setup*

- Created a calendar and set the default daily capacity to 8 hours.
- Marked 30 June as an exception day (non-working day).

!image-2025-06-23-11-54-47-490.png!



!image-2025-06-23-11-55-28-617.png!
 #  *Routing and Routing Task Configuration*

- Defined a routing and associated it with a routing task.
- Routing task includes:
  - Setup time: 8 hours
  - Run time: 8 hours
- Routing task is linked to a fixed asset, which in turn is assigned to the 
above calendar.

!image-2025-06-23-11-55-56-255.png!

!image-2025-06-23-11-56-16-151.png!



!image-2025-06-23-11-56-27-740.png!

!image-2025-06-23-11-56-35-835.png!
 #  *Fixed Asset Association*

- Verified that the fixed asset is correctly associated with the calendar 
containing the exception day.

!image-2025-06-23-11-56-49-284.png!
 #  *Production Run Creation*

- Created a production run for 4 quantity.
- Expected calculation:
  - 1 day for setup (8 hrs)
  - 4 days for run time (4 × 8 hrs)
  - Excluding weekends (Saturday, Sunday) and the exception day (30 June, 
Monday)
- Start Date: 27 June (Thursday)
- Expected Completion Date: 4 July (Thursday)
- Actual Completion Date (before fix): 3 July

!image-2025-06-23-11-57-05-685.png!



!image-2025-06-23-11-57-18-484.png!

*After Fix (Code Change)*

- The logic was updated to skip exception days during production scheduling.
- Now the system accurately excludes weekends and exception days in calculating 
end date.

!image-2025-06-23-11-57-28-311.png!

✅ Final Result:
With the fix in place, the job now correctly completes on 4 July, as expected.

 

> Calendar Exception Days Ignored in Production Run End Date Calculation.
> -----------------------------------------------------------------------
>
>                 Key: OFBIZ-13261
>                 URL: https://issues.apache.org/jira/browse/OFBIZ-13261
>             Project: OFBiz
>          Issue Type: Improvement
>          Components: manufacturing
>    Affects Versions: Upcoming Branch
>            Reporter: Yashwant Dhakad
>            Assignee: Yashwant Dhakad
>            Priority: Minor
>             Fix For: Upcoming Branch
>
>         Attachments: image-2025-06-23-11-54-47-490.png, 
> image-2025-06-23-11-55-28-617.png, image-2025-06-23-11-55-56-255.png, 
> image-2025-06-23-11-56-16-151.png, image-2025-06-23-11-56-27-740.png, 
> image-2025-06-23-11-56-35-835.png, image-2025-06-23-11-56-49-284.png, 
> image-2025-06-23-11-57-05-685.png, image-2025-06-23-11-57-18-484.png, 
> image-2025-06-23-11-57-28-311.png
>
>
> Within the *Manufacturing → Calendar* tab, users can define non-working days 
> using the *"Add Calendar Exception Day"* form. However, even after correctly 
> setting up exception days, the system fails to consider them when calculating 
> the end date of a production run.
> As a result, the projected end date does not align with real-world schedules, 
> leading to inaccuracies in planning and execution.



--