I am back, it was a complete non-event. A surprisingly large number of people 
actually used our secondary MX. DNSPark's system handled it very well...it went 
perfectly.


From: [email protected]<mailto:[email protected]> 
[mailto:[email protected]] On Behalf Of Kennedy, Jim
Sent: Thursday, July 18, 2013 10:37 AM
To: [email protected]<mailto:[email protected]>
Subject: [NTSysADM] Week long shutdown.

We are shutting our data center down for 7 days to repair the HAVAC/Electrical 
systems.  Long story but it needs to be done this way. Since we are a school 
district and it is summer we are just going to pull the plug on the network and 
let that summer staff fend for themselves. I have a secondary MX up with a hold 
and forward.

There are 4 offsite DC's that could be left running, but they will not be able 
to talk to each other, their connectivity is via the data center.  I am 
thinking shut them down too.

Any issues or concerns that come to mind for a week long downtime for AD?

Reply via email to