Areva to take 500 mln eur charge for Finnish reactor delay----- Original 
Message ----- 
From: Andr é Larivi è re-R é seau Sortir du nucl é aire 
To: rezo_nuke_info 
Sent: Friday, December 08, 2006 2:25 AM
Subject: [rezo-nuke-info] Areva to take 500 mln eur charge for Finnish reactor 
delay


AFX News Limited
Areva to take 500 mln eur charge for Finnish reactor delay
 - report - UPDATE
12.05.06, 6:16 AM ET

    
PARIS (AFX) - French nuclear energy giant Areva will take a charge of 500 mln 
eur this year for extra costs because work on the Olkiluoto 3 reactor in 
Finland is 18 months behind schedule, Les Echos reported, without naming its 
source.

'The initial calendar was perhaps too ambitious', the business daily cited an 
Areva spokesman as saying.

'The difficulties met since the start of work are not surprising. It is not a 
bag of chips that we are constructing in Finland but a nuclear reactor, which, 
what's more, is the first of its kind,' the spokesman said.

'Despite the 18 months delay, construction of the Finnish EPR (European 
pressrised water reactor) will not take any longer than usual nuclear sites. We 
tend to forget, but Chooz, the last reactor completed in France, by EDF, went 
into service four years later than envisaged,' he told Les Echos.

Finnish energy company TVO announced yesterday that construction of the world's 
first third-generation nuclear reactor is now 18 months behind schedule.

'Today's estimate is that the unit will be completed at the turn of 2010-2011,' 
the head of the project Martin Landtman said in a statement.

The reactor, Finland's fifth, was initially due to be operational in mid-2009. 
Construction began in August 2005.

A consortium comprising Areva and Siemens AG (nyse: SI - news - people ) is 
building the 3.8 bln eur reactor.

Areva admitted in July that the problems at the Olkiluoto 3 site will have a 
major impact on the company's full year results.

[EMAIL PROTECTED]




--------------------------------------------------------------------------------


International press review and information in english about nuclear and energy 
alternatives.
The information given on the list are not always representative of the Reseau 
"Sortir du nucleaire" opinion. 
To unsubscribe send an empty mail to [EMAIL PROTECTED]

Raspunde prin e-mail lui