Press release: 23.11.07

 

Ex-Head of Bulgarian Nuclear Safety Authority Speaks out against Belene Project

 

NGOs Accuse EU-Commission of Negligence

 

The controversy around the Bulgarian Government's plan to build a nuclear power 
plant (NPP) in an earthquake area close to the Romanian border has now reached 
Brussels. In a press conference today, Dr. Gueorgui Kastchiev, the former 
president of the Bulgarian Nuclear Regulatory Authority presented a list of 
concerns and stated, "I believe that the Belene nuclear power project must be 
stopped as soon as possible."

 

Kastchiev's statement comes at a sensitive time: The European Commission is due 
to issue an official opinion on the Belene project in early December. Although 
the Commission's opinion is non-binding, the Bulgarian government has 
nonetheless been lobbying hard for a positive assessment of the project, as 
this would enable it to apply for financial assistance to Euratom and the 
European Investment Bank. 

 

Today, a delegation with Dr. Kastchiev, who is currently senior nuclear expert 
at the Institute for Risk Analysis of the University of Vienna, Petko Kovatchev 
of the Bulgarian coalition "No to Belene!", Heffa Schücking of the German 
environment organisation urgewald, and Jan Haverkamp, Central European nuclear 
expert for Greenpeace, will meet with representatives of the European 
Commission to discuss the Commission's upcoming opinion on the Belene project 
under the Euratom treaty.

 

As Jan Haverkamp from Greenpeace says: "The importance of the Commission's 
decision cannot be overestimated. The Belene project has already run into great 
financial difficulties and without a Euratom loan it stands little chance of 
being completed." 

 

The plan to build an NPP near the town of Belene in northern Bulgaria has a 
chequered history: The plant was conceived and partially constructed in the 
1980s, scrapped in the 1990s and put back on the agenda in 2002. But the 
construction of the NPP is more or less on hold as private banks have been 
reluctant to participate in the controversial project. 

 

According to Dr. Kastchiev, "the Belene project poses intolerable safety and 
environmental risks. The lack of operational experience with the planned 
reactor type and the lack of qualified personnel and effective controls will 
undoubtedly lead to a poor quality of construction works," he predicts. "If one 
figures in the high seismic risks of the location and the low level of the 
nuclear safety culture in Bulgaria, it can only lead to one conclusion: This 
project must not go forward." 

 

Kastchiev has 34 years of experience in the nuclear power sector, half of them 
directly in the start-up and operation of NPPs with VVER type reactors. In 
regards to the upcoming decision, he says: "It would be a mistake if the 
Commission only bases its opinion on the design documentation, and ignores the 
on-the-ground reality of how such a project will be implemented in Bulgaria". 

 

It is not the first time that Kastchiev speaks out. In 2006, he blew the 
whistle on an incident in the Bulgarian Kozloduy nuclear power station, where 
one third of the regulation rods did not function. The Bulgarian authorities 
did not deem this incident important enough to register it with the 
International Atomic Energy Agency in Vienna, until Kastchiev made it public. 
Sofia then saw itself forced to upgrade the incident to the INES 2 level that 
indicates an incident with consequences for plant safety. "This is only one of 
many instances where Bulgarian nuclear authorities have tried to keep problems 
in the dark," says Kastchiev.  

 

Kastchiev furthermore pointed to the fact that the Bulgarian authorities deny 
the existence of any seismic risk. With a map from the European Seismological 
Commission from 2003, he illustrates why, for instance, in 1977 around 120 
people died in Svishtov, a town only 14 km away from Belene. "The denial of 
seismic risk from the site of Bulgarian authorities should sound alarm bells in 
the Commission," he says.

 

But apparently this is one of many issues that the Commission is bent on 
ignoring. Heffa Schücking from the German NGO says: "Our previous communication 
with the Commission shows that it is excluding some of the most relevant topics 
from its assessment of Belene, such as the quality of the Environmental Impact 
Assessment, the question of seismic risks and the low safety culture in the 
Bulgarian nuclear industry." She points out that due to the seismic risks even 
Soviet scientists demanded that Belene be taken off the list of possible sites 
for an NPP in the 1980s. According to Schücking, "the Commission's assessment 
procedures in regards to the Belene project are faulty, negligent and 
irresponsible. This is, after all, a matter where the health and safety of 
millions of Europeans is at risk.".

 

Schücking is not alone with her opinion. Over the past few days, the EU 
Commission has received thousands of emails from citizens throughout Europe, 
who are concerned about the Commission turning a blind eye to the project's 
risks. "We hope very much that public concern will lead the Commission to not 
play Russian roulette with our future by approving this project," says Petko 
Kovatchev, from the Bulgarian NGO Coalition BeleNE!

 

INFORMATION FOR THE EDITOR

 

Construction of the Belene nuclear power station started in 1985. The project 
was halted in 1991, and finally dropped in 1992 due to its environmental and 
economic risks. In 2003, however, the Bulgarian government restarted the 
project and in 2006, it decided to build two completely new reactors at the 
Belene site. The tender for construction was won by a consortium of the Russian 
firm Atomstroyexport and the French / German Areva NP to build an AES-92 
nuclear power station with two VVER 1000/466B reactors. This is a first of a 
kind reactor that has no operational record elsewhere in the world. The 
Environmental Impact Assessment report was finished in November 2004 - long 
before the reactor type was fixed -and has since then been subject to court 
procedures.

 

Dr. Gueorgui Kastchiev was one of the top managers of the Koszloduj nuclear 
power station from 1972 to 1989, and was head of the Bulgarian Nuclear Safety 
Authority from 1997 to 2001. He currently holds a position as Senior Nuclear 
Physicist at the Institute of Risk Research in Vienna.

 

A background briefing as well as fact sheets with a short chronology of the 
Belene project, its seismic risks and Dr. Kastchiev's presentation are 
available from [EMAIL PROTECTED] or [EMAIL PROTECTED] Queries for telephone 
interviews should be directed towards: +32 477 790 416 or +49 160 96761436

Raspunde prin e-mail lui