NWAM West: 8:30AM MPK/11:30AM BUR/4:30PM DUB

Attendees: Michael, Anurag, Erik, Alan, Victor, Karen, Renee 

1. Phase 1 status
   Schedule reports as of 10/8 are posted.
   Mostly on track right now; Alan and Anurag doing great, Renee and Michael
   starting to catch up.  Will check in with QE folks in East meeting.

   The ND (nwamd) tasks look to be the critical path in the implementation
   portion of the schedule; need to keep a close eye on how we're doing there.

2. Technical question: libinetcfg vs. libipadm.
   Though it looks like libipadm will eventually replace much if not all of
   the functionality in libinetcfg, our project cannot be dependent on the
   completion of libipadm.  Anurag is keeping up to date with the work being
   done on libipadm, and if it's possible for us to cut over before our
   integration we will; but for now we will continue to use libinetcfg.


NWAM East: 6:00PM MPK/9:00AM BJS

Attendees: Lizhong, Victor, Karen, Alex, John, Renee

1. Phase 1 status
   Reviewed impact of Lizhong being pulled onto another project part-time;
   need to be sure the revised schedule estimates are realistic!  Lizhong
   will review and get feedback to Karen in the next couple of days.  Karen
   will take all updates by COB Tuesday, 10/14, and have updated schedule
   ready for Victor on Wednesday.

2. Other issues?
   * We are doing a pretty good job of staying on track with the schedule;
     thanks to everyone on the team!

   * Need to start thinking about end-game process work:
     - Karen to check with Miguel about C-team inception and test sponsor
     - Renee will get PSARC inception scheduled this week


-renee