NWAM West: 8:30AM MPK/11:30AM BUR/4:30PM DUB

Attendees: Darren, Victor, Michael, Karen, Steff, Anurag, Alan, Renee

1. Phase 1 status
   - Schedule reports as of 12/3 are posted.

   - Key dependency for test dev right now is ND6.  Michael is getting
     close on that; also, test assertion work can likely move forward
     with more spec details of what Michael's implementing.  Will look
     at that during Alan, Anurag, Michael and Renee's meeting tomorrow.

   - Travel to MPK in February: need to be confident that all dev work
     will be complete then in order to make that time most productive;
     and we need to book travel soon.  Need to identify long pole and
     determine when it will be complete; will need input from test dev
     engineers in NWAM East meeting.

2. 2008.11 Bugs
   - Incoming rate significantly slowed.  Alan working on triage.
     Thanks, Alan!

   - Jim pushed a bunch of fixes last night, will be in 105; Darren
     has some additional GUI fixes that will follow next week, and
     will be in 106.  Anurag's fix also coming soon.

3. Docs
   - Steff looking at split between JDS help and sys admin guides;
     the latter will be more focused on concepts, while the former
     will help with tasks.


NWAM East: 5:00PM MPK/9:00AM BJS

Attendees: Alex, Lizhong, Victor, John, Renee

1. Review of earlier meeting; see notes above.

2. Schedule updates

   Alex: has run into some issues that are blocking his work; please
      let the team know that this is happening so we can help.
   Lizhong: working on other projects, but still targets 1/9 date for
      CLI2-4.
   John: has also been pulled off on other things, sent some notes to
      Karen about changes to his schedule, need to review.