David,

David E. Jones wrote:

Splitting the shipment if partially received is an interesting idea, but why not just partially receive the shipment and issue specific quantities as they come in and wait to set the status to received until the entire shipment is received? There may be some issues with this, but it would be more consistent with how we handle orders, etc.

-David


really thanks for your prompt response.
What you are suggesting is a good approach, it's simple and it works fine (I've tested it). However, if we want to record the actual shipments from the supplier the alternative approach that I've implemented could be sometimes useful.

Let's say that I've created a purchase order for 100 units of WG-1111 (my favorite widget!); the supplier says he will send all the items with one shipment; however when the shipment arrives, I discover that he sent me only 90 units; I'll have to call the supplier and we will have to schedule another shipment for the remaining 10 units (let's say for the next month): it would be nice to close the first shipment and create a new one. Or I could agree with the supplier to close the shipment and cancel the remaining 10 units from the purchase order.

Does it make sense?

Jacopo

Reply via email to