I apologize for my lack of clarity in earlier communications.

In my snv_97 rules of engagement note [1], when I wrote that "the onnv_97 
gate will *NOT* open immediately after onnv_96 closes. Instead, there will 
be a delay of 12-24 hours while we change filesystems and mountpoints and 
such," what I really meant to say was:

        As of 23:00 PDT on Monday, August 4, the ON gate will close, and
        will remain closed until further notice.

And when I wrote that "Beginning on Tuesday, August 5, we will begin 
taking integrations to the new, Mercurial gate.  The first few such 
integrations will be by invitation of the gatekeepers, and will be 
coordinated to ensure that everything on the gate and build machines is 
working as expected," what I really meant to say was:

        You may not push to the new Mercurial gate until we tell you it's
        OK to do so.

As it is now well past the aforementioned time, allow me to repeat myself: 
the ON gate is closed until further notice.

Thank you.

--Mark

PS Yes, I'm a litle bit cranky.  Someone just attempted to push to the new 
gate, which we have barely created, let alone finished setting up.

[1] http://www.opensolaris.org/os/community/on/flag-days/pages/2008080401/

Reply via email to