Hi PTLs,

I wanted to follow up on the discussion we had at weekly PTL meeting today.

RC1 is coming this Thursday, May 3. As usual, fill out the 
template<https://wiki.onap.org/display/DW/Deliverables+for+RCx+Milestone+Checklist+Template>.
 Please make it possible to join the bridge or send out a delegate. TSC may 
have questions on which we expect timely responses.

Criteria for RC1 as discussed on TSC meeting is:



1.       Pass OOM Deployment (and heat for contingency)

2.       Pass Pair Wise testing for all projects

3.       Pass vFW / vLB + vCPE + VoLTE regression use case for projects on 
critical path

Please update the Pair Wise status in wiki from 
https://wiki.onap.org/display/DW/Integration+Weather+Board

For the vFW / vLB + vCPE + VoLTE  Use cases, Helen and Brian will confirm the 
status during RC1.

Let me know if you have any question, I will be glad to help.

Thanks,
Gildas

[HuaweiLogowithName]
Gildas Lanilis
ONAP Release Manager
Santa Clara CA, USA
[email protected]
Mobile: 1 415 238 6287

_______________________________________________
ONAP-TSC mailing list
[email protected]
https://lists.onap.org/mailman/listinfo/onap-tsc

Reply via email to