Hi PTLs,

FYI, I have updated the wiki with the RCO materials, current status and Actions 
Items at 
https://wiki.onap.org/display/DW/Project+Status+in+Casablanca+Release#ProjectStatusinCasablancaRelease-RC0Status.

Actions items are:

1.       Pair Wise Testing: MUST be completed by RC1. Master page is available 
at 
https://wiki.onap.org/display/DW/Integration+Weather+Board+for+Casablanca+Release
 . Please used the child page relevant to your project.

2.       HealthCheck, focus on OOM environment, to be addressed by Monday, Oct 
15. Grafana graph at 
http://onapci.org/grafana/d/8cGRqBOmz/daily-summary?panelId=8&fullscreen&orgId=1
 is the dashboard to use.

3.       Docker artifacts: to be delivered by Friday, Oct 12 COB. For those 
delivering Docker Images, the images MUST be in Docker Release repo. Detailled 
process is posted in 
wiki<https://wiki.onap.org/display/DW/Release+Version+of+Component>. For those 
projects who are not delivering Docker images (Music, Modelling, VVP), they 
still need to release in Nexus-Release their deliverables. Same process as for 
Docker images. Same process for those delivering Python in Nexus3 Pypi.
Let me know if you have any questions, I will be glad to help.

Thanks,
Gildas

[HuaweiLogowithName]
Gildas Lanilis
ONAP Release Manager
Santa Clara CA, USA
[email protected]
Mobile: 1 415 238 6287


-=-=-=-=-=-=-=-=-=-=-=-
Links: You receive all messages sent to this group.

View/Reply Online (#3880): https://lists.onap.org/g/onap-tsc/message/3880
Mute This Topic: https://lists.onap.org/mt/27260712/21656
Group Owner: [email protected]
Unsubscribe: https://lists.onap.org/g/onap-tsc/leave/2743226/1412191262/xyzzy  
[[email protected]]
-=-=-=-=-=-=-=-=-=-=-=-

Reply via email to