Hi Kevin,

Thanks for the update.

Use case testing does not need to be completed until Sign Off.  For RC, you
just need to complete the release management tasks for RC
<https://jira.onap.org/issues/?jql=labels%20%3D%20relman_req_rc%20AND%20fixVersion%20%3D%20%22Kohn%20Release%22%20AND%20cf%5B10001%5D%20%3D%20REQ-1215>.


David

On Wed, Oct 26, 2022 at 1:46 PM Kevin Tang <[email protected]> wrote:

> Hi David,
>
> Just in case that you did not get my previous email, which is copied below.
>
> E2E network slicing use case testing is currently blocked by 2 bugs/issues
> (error in the core NSSMF activate flow and Postgres exception with latest
> uui-server image), for which Jira issues have been created. The team is
> working on the fixes, but due to limited resources and holidays, current
> estimation is that we need one week to fix the bugs/issues and another week
> to complete the tests. I have also given an update on this in the Oct 24th
> Requirements Subcommittee meeting while the team was still evaluating the
> time to complete at that time.
>
> Thanks,
> Kevin
>
> On Wed, Oct 26, 2022 at 12:24 PM David McBride <
> [email protected]> wrote:
>
>> *Kohn Release*
>>
>>    - Schedule <https://wiki.onap.org/x/2gWsBw>
>>       - RC is scheduled for *TOMORROW* (Oct 27)
>>       - Sign Off is scheduled for Nov 10
>>    - Milestone Status <https://wiki.onap.org/x/8gWsBw>
>>    - Integration Testing Status
>>    
>> <https://wiki.onap.org/display/DW/2%3A+Kohn+Release+Integration+Testing+Status>
>>    - Integration Blocking Issues
>>    <https://wiki.onap.org/display/DW/Kohn+Integration+Blocking+points>
>>    - Integration Test Results (daily master)
>>    
>> <https://logs.onap.org/onap-integration/daily/onap-daily-dt-oom-master/2022-10/26_05-32/>
>>    - Open issue status and trend
>>    <https://jira.onap.org/secure/Dashboard.jspa?selectPageId=12100>
>>    - Unmaintained repo resolution activity
>>    <https://wiki.onap.org/x/LQtHC>
>>
>>
>> *London Release*
>>
>>    - Schedule <https://wiki.onap.org/x/fwDiC>
>>       - Kickoff was last week.
>>       - M1 is scheduled for Dec 1
>>    - Last week, at the ODL/ONAP integration sync meeting
>>    <https://wiki.lfnetworking.org/x/LgDJB>, a plan was agreed to for ODL
>>    integration in the London release.
>>
>>
>> Let me know if you have any questions.
>>
>> David
>>
>> --
>> *David McBride *(pronounce <https://nmdrp.me/davidmcbride>)
>> Senior Technical Community Architect
>> Linux Foundation Networking (LFN)
>> Mobile: +1.805.276.8018
>> Email: [email protected]
>>
>> 
>
>

-- 
*David McBride *(pronounce <https://nmdrp.me/davidmcbride>)
Senior Technical Community Architect
Linux Foundation Networking (LFN)
Mobile: +1.805.276.8018
Email: [email protected]


-=-=-=-=-=-=-=-=-=-=-=-
Links: You receive all messages sent to this group.
View/Reply Online (#9062): https://lists.onap.org/g/onap-tsc/message/9062
Mute This Topic: https://lists.onap.org/mt/94589358/21656
Mute #weeklyupdate:https://lists.onap.org/g/onap-tsc/mutehashtag/weeklyupdate
Group Owner: [email protected]
Unsubscribe: 
https://lists.onap.org/g/onap-tsc/leave/2743226/21656/1412191262/xyzzy 
[[email protected]]
-=-=-=-=-=-=-=-=-=-=-=-


Reply via email to