Team,

This past Thursday, the TSC agreed that the Kohn release was not ready for
Sign Off. The key reasons were:

   - Daily testing not yet available on the release branch
   - Insufficient progress on release management tasks
   - Significant effort remaining to complete documentation

The TSC agreed to push out Sign Off by 3 weeks to Dec 1 due to conflicts
with ONE Summit next week, and the Thanksgiving holiday in the U.S. the
following week.

In addition, in order to avoid overlapping schedules, the London M1
milestone, which was originally scheduled for Dec 1, was pushed out one
week to Dec 8. The remainder of the London schedule is unchanged.

The Kohn release schedule <https://wiki.onap.org/x/2gWsBw> and the London
release schedule <https://wiki.onap.org/x/fwDiC> have been updated to
reflect the decisions by the TSC.

Let me know if you have any questions.

David

-- 
*David McBride *(pronounce <https://nmdrp.me/davidmcbride>)
Senior Technical Community Architect
Linux Foundation Networking (LFN)
Mobile: +1.805.276.8018
Email: [email protected]


-=-=-=-=-=-=-=-=-=-=-=-
Links: You receive all messages sent to this group.
View/Reply Online (#9106): https://lists.onap.org/g/onap-tsc/message/9106
Mute This Topic: https://lists.onap.org/mt/94991585/21656
Mute #kohn:https://lists.onap.org/g/onap-tsc/mutehashtag/kohn
Mute #london:https://lists.onap.org/g/onap-tsc/mutehashtag/london
Group Owner: [email protected]
Unsubscribe: 
https://lists.onap.org/g/onap-tsc/leave/2743226/21656/1412191262/xyzzy 
[[email protected]]
-=-=-=-=-=-=-=-=-=-=-=-


Reply via email to