Hello everyone,

After a couple weeks of suspense and anguish, you are now at last reading my 
first official communication as release manager [RM] for 2.5.  In the interest 
of general efficiency, and to encourage dialog over unnecessary detail, I will 
try to be succinct.

Announcements:
1) Hello world - For any who do not know, I am the release manager for 
Evergreen 2.5.  Unless you were at the dev meeting, you probably don't know, 
because I haven't (publicly) done anything yet.

2) Mailing list intentions - Rather than double-post everything for the next 4 
months, future "official" 2.5 RM communications will typically be on the 
*general* list only.  Every developer should be on the general list, and my 
primary goal will be to keep everybody in the loop, not just the developers.  
If you are a dev and are not on the general list (and you care about these 
messages, or Evergreen in general), please subscribe.

3) Mailing list "tag" - I'll be "tagging" any RM-specific emails with [RM2.5] 
in the subject line.  I don't know if this will be useful, but it seems like it 
might be helpful to me at least.

4) Concerning milestones
4a) Changing of "alpha" milestone - As implied by my original proposal, the 
current "2.5-alpha1" milestone is going to be renamed to "2.5-M1".  If you have 
anything in Launchpad tagged "alpha1" which you actually want to put off until 
then, you will need to move it to the new "alpha1" milestone (see next).
4b) Creating "planning" milestones - After alpha1 is renamed, I will 
immediately create an M2 milestone and a new alpha1 milestone.  These are meant 
to provide a way to set expectations for feature branch completion goals.  You 
are encouraged to post your feature descriptions as early as possible.
4c) Setting milestones based on the roadmap [1] - Any current feature tickets 
on the roadmap with a 'pullrequest' tag but no milestone will be set to M1.  
Any without a 'pullrequest' tag will be initially set to M2.  If you are 
heading up development of any features, please feel free to adjust the goal 
milestones as appropriate.

5) Whitespace fix (revised plans) - There was concern at the dev meeting about 
my initial plan to split up the mass whitespace fix into three passes.  After 
further consideration and process testing, I now feel more confident that doing 
the fix all at once is both doable and preferable.  Sometime in the next week 
or so, I will make a first pass at creating some process instructions/tips and 
post them to the wiki.  The current intention is that the mass whitespace fix 
will happen immediately after the M1 phase.


Important Dates:
5/27 - (suggested) last day to target bugs/features for M1
6/3 - goal date for having all M1 bugs/features committed to master


So, developers, testers, and other contributors, the first big push for 2.5 
commits will start 1.5 weeks from now and continue for 1 week.  I fully 
understand that there will be personal conflicts which prevent participation in 
this push, but with a little focus (and perhaps some poking and prodding), I am 
confident we can make it happen.

As always, questions, comments, concerns, and suggestions are welcome.

Sincerely,
Dan