Current Dev Position: YP 3.3 M2 development

Next Deadline: 18th January 2021 YP 3.3 M2 build 

 

Next Team Meetings:

*       Bug Triage meeting Thursday Jan. 21st at 7:30am PDT (
<https://zoom.us/j/454367603?pwd=ZGxoa2ZXL3FkM3Y0bFd5aVpHVVZ6dz09>
https://zoom.us/j/454367603?pwd=ZGxoa2ZXL3FkM3Y0bFd5aVpHVVZ6dz09)
*       Monthly Project Meeting Tuesday Feb. 2nd at 8am PDT (
<https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09>
https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09
<https://zoom.us/j/990892712> )
*       Weekly Engineering Sync Tuesday Jan. 19th at 8am PDT (
<https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09>
https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09
<https://zoom.us/j/990892712> )
*       Twitch -  See https://www.twitch.tv/theyoctojester

 

Key Status/Updates:

*       YP 3.3 M2 is due to be built once the currently queued patches are
stalised.
*       YP 3.1.5 has been built and is through QA and likely to be released
imminently after TSC review.
*       We're pleased to announce that Bootlin are going to be helping with
the build and integration work for the project, we'd like to welcome them on
board and also thank the projects member companies for making this possible.
*       Builds are continuing to show some intermittent instability.
Unfortunately we also suffered NAS issues and whilst there has been no data
loss, recovery of the system is slowing the autobuilder temporarily.
*       Intermittent autobuilder issues continue to occur and with more
invasive changes and higher rebuild rates, the numbers are increasing again.
You can see the list of failures we're continuing to see by searching for
the "AB-INT" tag in bugzilla:
<https://bugzilla.yoctoproject.org/buglist.cgi?quicksearch=AB-INT>
https://bugzilla.yoctoproject.org/buglist.cgi?quicksearch=AB-INT

 

Ways to contribute:

*       There are bugs identified as possible for newcomers to the project:
<https://wiki.yoctoproject.org/wiki/Newcomers>
https://wiki.yoctoproject.org/wiki/Newcomers
*       There are bugs that are currently unassigned for YP 3.3. See:
<https://wiki.yoctoproject.org/wiki/Bug_Triage#Medium.2B_3.3_Unassigned_Enha
ncements.2FBugs>
https://wiki.yoctoproject.org/wiki/Bug_Triage#Medium.2B_3.3_Unassigned_Enhan
cements.2FBugs
*       We'd welcome new maintainers for recipes in OE-Core. Please see the
list at:
<http://git.yoctoproject.org/cgit.cgi/poky/tree/meta/conf/distro/include/mai
ntainers.inc>
http://git.yoctoproject.org/cgit.cgi/poky/tree/meta/conf/distro/include/main
tainers.inc and discuss with the existing maintainer, or ask on the OE-Core
mailing list. We will likely move a chunk of these to "Unassigned" soon to
help facilitate this.

 

YP 3.3 Milestone Dates:

*       YP 3.3 M2 build date 2021/01/18
*       YP 3.3 M2 Release date 2021/01/29
*       YP 3.3 M3 build date 2021/03/01
*       YP 3.3 M3 Release date 2021/03/12
*       YP 3.3 M4 build date 2021/04/05
*       YP 3.3 M4 Release date 2021/04/30

 

Planned upcoming dot releases:

*       YP 3.1.5 is out of QA.
*       YP 3.2.2 build date 2021/02/08
*       YP 3.2.2 release date 2021/02/19
*       YP 3.1.6 build date 2021/02/22
*       YP 3.1.6 release date 2021/03/05
*       YP 3.1.7 build date 2021/03/22
*       YP 3.1.7 release date 2021/04/02

 

Tracking Metrics:

*       WDD 2634 (last week 2587) (
<https://wiki.yoctoproject.org/charts/combo.html>
https://wiki.yoctoproject.org/charts/combo.html)
*       Poky Patch Metrics  

*       Total patches found: 1292 (last week 1298)
*       Patches in the Pending State: 503 (39%) [last week 503 (39%)]

 

The Yocto Project's technical governance is through its Technical Steering
Committee, more information is available at:

 <https://wiki.yoctoproject.org/wiki/TSC>
https://wiki.yoctoproject.org/wiki/TSC

 

The Status reports are now stored on the wiki at:
<https://wiki.yoctoproject.org/wiki/Weekly_Status>
https://wiki.yoctoproject.org/wiki/Weekly_Status

 

[If anyone has suggestions for other information you'd like to see on this
weekly status update, let us know!]

 

Thanks,

 

Stephen K. Jolley

Yocto Project Program Manager

*    Cell:                (208) 244-4460

* Email:              [email protected]
<mailto:[email protected]> 

 

-=-=-=-=-=-=-=-=-=-=-=-
Links: You receive all messages sent to this group.
View/Reply Online (#146991): 
https://lists.openembedded.org/g/openembedded-core/message/146991
Mute This Topic: https://lists.openembedded.org/mt/79954061/21656
Group Owner: [email protected]
Unsubscribe: https://lists.openembedded.org/g/openembedded-core/unsub 
[[email protected]]
-=-=-=-=-=-=-=-=-=-=-=-

Reply via email to