Title: Eric CAUDAL
The UoM is defined in the product used in the relevant user.
You cannot convert PCE to hours if they are not in the same UoM category.
But you can say 1 day = 8 h in same category: OpenERP will take care of the conversion.
Eric Caudal
CEO
--
Elico Corporation, Shanghai branch
OpenERP Premium Certified Training Partner 
Cell: + 86 186 2136 1670
Office: + 86 21 6211 8017/27/37
Skype: elico.corp
[email protected]
http://www.elico-corp.com

Elico
          Corp
On 12/27/2012 09:32 AM, Dale E. Moore wrote:
I'm sorry Cristian; I've tried several times to understand your two questions and I'm pretty sure I don't understand what you are asking.

You said "Hello, so if its dont configured the worktime in project, hour is the UoM by default ?" I think you were asking "Is Work Task entry default UoM Hour?" I believe the answer is yes, especially since the relevant field is "Time Spent."

You said "And is used to compute the task and project progress ?" I think you were asking "Is 'Time Spent' used to compute task and project progress?" I believe the answer to that is yes, because; task and project progress seem to increase by 'Time Spent' amounts.

Please let me know if I've misunderstood your questions!

You raise a relevant point; how would the current Project entry work by only partially shifting to PCE, Piece or Unit entry. Shouldn't I also compute task and project progress? I think you are right, thanks for the insight! I should look through the entire Project to see how Piece instead of Time would be calculated.

And this raises another question. Where do I retain the calculation 1 Piece = XYZ hours? This sounds more like a manufacturing effect than project management.

I appreciate y'alls insights!



On Wed, Dec 26, 2012 at 9:26 AM, Ovnicraft <[email protected]> wrote:



On Wed, Dec 26, 2012 at 1:33 AM, jeff.wang <[email protected]> wrote:
Hi Dale,

  Hour is UOM of time, you need use a time UOM for a task, eg, day or week or month or maybe year.

Hello, so if its dont configured the worktime in project, hour is the UoM by default ? 
And is used to compute the task and project progress ?

Regards, 

  PCE is piece, do you want a piece of task ? never.

  so try to input day or hour in the UOM for your product. good luck !

------------------
Jeff Wang |  [email protected] | 18016291663 | 02158980787
@OpenERP_Jeff "As simple as possible, As complex as needed"
Maintainer of Open ERP china community 
 


------------------ Original ------------------
From:  "Dale E. Moore"<[email protected]>;
Date:  Wed, Dec 26, 2012 10:35 AM
To:  "openerp-community"<[email protected]>;
Subject:  [Openerp-community] v61 Tasks Work employee product is units?

When I enter the Time Spent for a Task Work and the Analytic
User/Product Rel. is a UoM other than time, like PCE, I get
"Conversion from Product UoM Hour to Default UoM PCE is not possible
as they both belong to different Category!."

Have I missed configuring my installation to allow PCE UoM entry for
Task Work, or is that something that's not allowed?

I look forward to hearing from you,
[email protected]

_______________________________________________
Mailing list: https://launchpad.net/~openerp-community
Post to     : [email protected]
Unsubscribe : https://launchpad.net/~openerp-community
More help   : https://help.launchpad.net/ListHelp

_______________________________________________
Mailing list: https://launchpad.net/~openerp-community
Post to     : [email protected]
Unsubscribe : https://launchpad.net/~openerp-community
More help   : https://help.launchpad.net/ListHelp




--
Cristian Salamea
@ovnicraft



_______________________________________________
Mailing list: https://launchpad.net/~openerp-community
Post to     : [email protected]
Unsubscribe : https://launchpad.net/~openerp-community
More help   : https://help.launchpad.net/ListHelp

_______________________________________________
Mailing list: https://launchpad.net/~openerp-community
Post to     : [email protected]
Unsubscribe : https://launchpad.net/~openerp-community
More help   : https://help.launchpad.net/ListHelp

Reply via email to