Review: Needs Fixing

Does not work as expected.
Suppose you have a project P with two tasks A and B, both estimated to 10 hours 
of work.
Start both tasks, and create a task work line of 5 hours in task A.
The progress values are: A 50%, B 0%, P 25% (as shown in page views).
The gantt chart of tasks displays: A 50%, B 0%, P 50%.
The values of progress on the project and user levels are wrong.

Please fix this issue.  Quite possibly the error is in the web client.

Thanks,
Raphael

-- 