Review: Needs Fixing Does not work as expected. Suppose you have a project P with two tasks A and B, both estimated to 10 hours of work. Start both tasks, and create a task work line of 5 hours in task A. The progress values are: A 50%, B 0%, P 25% (as shown in page views). The gantt chart of tasks displays: A 50%, B 0%, P 50%. The values of progress on the project and user levels are wrong.
Please fix this issue. Quite possibly the error is in the web client. Thanks, Raphael -- https://code.launchpad.net/~openerp-dev/openobject-addons/trunk-bug-908764-kjo/+merge/87731 Your team OpenERP R&D Team is subscribed to branch lp:~openerp-dev/openobject-addons/trunk-bug-908764-kjo. _______________________________________________ Mailing list: https://launchpad.net/~openerp-dev-gtk Post to : [email protected] Unsubscribe : https://launchpad.net/~openerp-dev-gtk More help : https://help.launchpad.net/ListHelp