Review: Needs Fixing
we should not allow to move a task to a stage which is not belongs to the
project's stages.
eg: we have a Project P1 with
With stages s1, s2
Tasks T1
So this task T1 should never allow to move to a stage rather than s1 and s2
Thanks,
Purnendu Singh
--
https://code.launchpad.net/~openerp-dev/openobject-addons/trunk-state_sync_with_kanban-task-mdi/+merge/102511