Public bug reported:
I have got a huge issue with projects that I think could be considered a
bug/regression from 5.0 to 6.0 since (if I'm not mistaken) it was
correct in 5.0 before unifying projects and analytic accounts?
>From 6.0, projects haven't got a real project parent_id but only
analytic account parent_id. This is right to control costs of the
project but this way I can find these problems:
1. System is not drawing the complet project Gantt view but only one level
project Gant view.
2. Each project computes the stimated hours of their own tasks, I can not
see the real stimated hour cost in a multilevel project. Grand-child stimated
hours are not computed, neither are real dedicated hours.
3. If you set final data in a task manually, only his parent (project) is
shown correctly on task gantt view. Same project in project Gantt view is not
correctly drawn.
There is more issues but these are the huges ones since I can not see the real
planning for one big project.
It's happening in both versions 6.0 and 6.1.
To reproduce the bug:
I have just installed clean 6.1 nightly building, with new database only
project app installed. I created 2 projects
Parent project
Project 1
Task 1 Stimated 5 hours
System is not drawing correct parent project gantt
I can see 5 stimated hours in Project1 but not in Parent project.
If you set final data in task 1, only his parent is shown correct on task gantt
view.
Thank you:
Ana
** Affects: openobject-addons
Importance: Undecided
Status: New
--
You received this bug notification because you are a member of OpenERP
Indian Team, which is subscribed to OpenERP Addons.
https://bugs.launchpad.net/bugs/1014867
Title:
Multilevel projects from 5.0 to 6.0 / 6.1
Status in OpenERP Addons (modules):
New
Bug description:
I have got a huge issue with projects that I think could be considered
a bug/regression from 5.0 to 6.0 since (if I'm not mistaken) it was
correct in 5.0 before unifying projects and analytic accounts?
From 6.0, projects haven't got a real project parent_id but only
analytic account parent_id. This is right to control costs of the
project but this way I can find these problems:
1. System is not drawing the complet project Gantt view but only one
level project Gant view.
2. Each project computes the stimated hours of their own tasks, I can not
see the real stimated hour cost in a multilevel project. Grand-child stimated
hours are not computed, neither are real dedicated hours.
3. If you set final data in a task manually, only his parent (project) is
shown correctly on task gantt view. Same project in project Gantt view is not
correctly drawn.
There is more issues but these are the huges ones since I can not see the
real planning for one big project.
It's happening in both versions 6.0 and 6.1.
To reproduce the bug:
I have just installed clean 6.1 nightly building, with new database only
project app installed. I created 2 projects
Parent project
Project 1
Task 1 Stimated 5 hours
System is not drawing correct parent project gantt
I can see 5 stimated hours in Project1 but not in Parent project.
If you set final data in task 1, only his parent is shown correct on task
gantt view.
Thank you:
Ana
To manage notifications about this bug go to:
https://bugs.launchpad.net/openobject-addons/+bug/1014867/+subscriptions
_______________________________________________
Mailing list: https://launchpad.net/~openerp-india
Post to : [email protected]
Unsubscribe : https://launchpad.net/~openerp-india
More help : https://help.launchpad.net/ListHelp