Dear all,
I have a 4-way multi-master openldap servers running in version 2.4.11. Let's
say the servers name are A, B, C, D.
I have another 4-way multi-master openldap servers running in version 2.4.40.
Let's say the servers name are W,X,Y,Z.
What's the proper procedure of migrating the data from servers A,B,C,D to
W,X,Y,Z ?
My procedure is as follows :- Export data from server A using slapcat command.-
Delete the first 6 lines of the ldif files (the lines contains the
contextCSN).- Shutdown the process slapd in servers W,X,Y,Z and remove all the
openldap data files under /usr/local/var/openldap-data.- Import the ldif files
to server W, then start the slapd process in server W.- Export the ldif files
from server W.- Import the ldif files to server X,Y,Z respectively.- Start the
slapd process in X,Y,Z.
What I observe is that all four servers then has 100% CPU and never drop back
to idle ?
So, is there anything I do wrong ?
Thanks