Next week we'll start with the release engineering process for
OpenPKG 2.1. The project manager is (again) Thomas Lotterer
<[EMAIL PROTECTED]>. According to our Engineering Phases (see
http://www.openpkg.org/doc/slideset/openpkg/slide-019-m.html), the
final release of OpenPKG 2.1 is planned for 30-Jun-2004.
The major goals for OpenPKG 2.1 are:
- available contributor environment
- further tool chain integration
- additional RPM extensions (hooks, etc)
- latest vendor versions
- latest platform support
- official slideset material
The release engineering timeline for OpenPKG 2.1 is:
==============------ Buildfarm HW
==============------ Buildfarm SW
-------=======------ Server Env
----=====================------- Development
-------=====================-- - - - - - - - - - Bugfixing
---==== Blessing
== CVS Branching
(09-Jun) # SNAPSHOT
==================-- RSE Vacation
===============----- Testing
===============----- Documentation
---------------===== Press Release
(30-Jun) # RELEASE
-|------|------|------|------|------|------|------|------|------|----------->
|MTWTFS|MTWTFS|MTWTFS|MTWTFS|MTWTFS|MTWTFS|MTWTFS|MTWTFS|MTWTFS|...
| CW19 | CW20 | CW21 | CW22 | CW23 | CW24 | CW25 | CW26 | CW27 |...
Legend: (=) Primary Period (-) Extended Period (#) Milestone
As you can see, we'll again perform various tasks in parallel to
optimize the process. More details about the individual sub-tasks you
can find under http://cvs.openpkg.org/openpkg-re/todo.txt
All contributors are now encouraged to review their own problem and
patch queue and send us *NOW* the information about critial issues which
should be addressed in OpenPKG 2.1 -- or the resolving of the issues
have to wait until OpenPKG 2.2 ;-) Thanks.
--
The OpenPKG Project Ralf S. Engelschall
Cross-Platform Unix Software Packaging OpenPKG Project Leader
http://www.openpkg.org/ [EMAIL PROTECTED]