On 11/18/2013 06:47 PM, Joshua Harlow wrote:
An idea related to this, what would need to be done to make the DB have
the exact state that a compute node is going through (and therefore the
scheduler would not make unreliable/racey decisions, even when there are
multiple schedulers). It's not like we are dealing with a system which
can not know the exact state (as long as the compute nodes are connected
to the network, and a network partition does not occur).

How would you synchronize the various schedulers with each other? Suppose you have multiple scheduler nodes all trying to boot multiple instances each.

Even if each at the start of the process each scheduler has a perfect view of the system, each scheduler would need to have a view of what every other scheduler is doing in order to not make racy decisions.

I see a few options:

1) Push scheduling down into the database itself. Implement scheduler filters as SQL queries or stored procedures.

2) Get rid of the DB for scheduling. It looks like people are working on this: https://blueprints.launchpad.net/nova/+spec/no-db-scheduler

3) Do multi-stage scheduling. Do a "tentative" schedule, then try and update the DB to reserve all the necessary resources. If that fails, someone got there ahead of you so try again with the new data.