Hi everyone,

As you probably know, the Juno-3 milestone should be published Thursday
this week, and with it comes the Juno feature freeze. The general
schedule is as follows:

Tuesday:
Defer/-2 blueprints that will obviously not get the required approvals
in the next 20 hours. Review and approve as much as you can.

Wednesday:
Everything that is not approved and in-flight in the gate should be
deferred/-2.

Thursday:
Wait for the last approved stuff to make it through the gate and publish
the milestone.

Friday:
Start considering feature freeze exceptions for critical Juno features.

That really means *today is the last day for feature reviews*.
So please plan that extra review effort today, rather than tomorrow !

Thanks everyone for helping us do a successful Juno release.

-- 
Thierry Carrez (ttx)

_______________________________________________
OpenStack-dev mailing list
OpenStack-dev@lists.openstack.org
http://lists.openstack.org/cgi-bin/mailman/listinfo/openstack-dev

Reply via email to