Hello everyone,

We keep putting our best efforts to hit Hard Code Freeze goals. Latest test results are 68% pass rate for Ubuntu and 65% for CentOS. Once the remaining bugs are closed, we will be able to hit 70% target for sure. Based on the feedback from Engineering leads, with current incoming/outgoing ratio the chance to close all remaining bugs by Friday this week is high and we'll then need a couple of days to settle down with Release Candidate. So, we will target June 2nd for Hard Code Freeze.

Our history of releases show that we need 3 additional weeks on average to transform Release Candidate to final RTM build, so we'll target GA date is June 23rd.

I have updated the schedule with the above dates. Thank you.

--
EugeneB