Hello everyone,
We keep putting our best efforts to hit Hard Code Freeze goals. Latest
test results are 68% pass rate for Ubuntu and 65% for CentOS. Once the
remaining bugs are closed, we will be able to hit 70% target for sure.
Based on the feedback from Engineering leads, with current
incoming/outgoing ratio the chance to close all remaining bugs by Friday
this week is high and we'll then need a couple of days to settle down
with Release Candidate. So, we will target June 2nd for Hard Code Freeze.
Our history of releases show that we need 3 additional weeks on average
to transform Release Candidate to final RTM build, so we'll target GA
date is June 23rd.
I have updated the schedule with the above dates. Thank you.
--
EugeneB
__________________________________________________________________________
OpenStack Development Mailing List (not for usage questions)
Unsubscribe: [email protected]?subject:unsubscribe
http://lists.openstack.org/cgi-bin/mailman/listinfo/openstack-dev