Oleg, thanks for the provided information. As discussed verbally, most
core reviewers are now busy with fixing critical bugs, so you might get
delayed responses. Keeping in mind, let's target Wednesday, Aug 5 as the
last deadline. With that said, let's minimize review iterations so core
reviewers avoid unnecessary focus switch.
--
EugeneB
Oleg Gelbukh <mailto:[email protected]>
31 июля 2015 г., 23:00
Team,
I'd like to inform you about status of FF Exception for Cluster
Upgrade feature.
The due date for the exception was Jul 30th. We had 4 patches to merge
in the beginning of the work.
During review it was decided that changes to the core of Nailgun
should be split into separate CR, making it 5 patches. In a course of
development we also hit a glitch in deep layers of networking modules
of Nailgun [1]. This slowed down the development and review process,
and as a result we only merged 1 patch out of 5 by the due date of the
FFE.
I would like to ask for 4 more days of FFE, which effectively will
move the due date to Aug 3rd.
[1] https://bugs.launchpad.net/fuel/+bug/1480228
--
Best regards,
Oleg Gelbukh
__________________________________________________________________________
OpenStack Development Mailing List (not for usage questions)
Unsubscribe: [email protected]?subject:unsubscribe
http://lists.openstack.org/cgi-bin/mailman/listinfo/openstack-dev
__________________________________________________________________________
OpenStack Development Mailing List (not for usage questions)
Unsubscribe: [email protected]?subject:unsubscribe
http://lists.openstack.org/cgi-bin/mailman/listinfo/openstack-dev