On Wed, Sep 02, 2015 at 09:07:57AM -0400, Sean Dague wrote: > Today's gate firedrill #2 is the fact that in the last 12 hours heat's > functional tests went to 100% failure - http://goo.gl/YeVrD0 > > There are current 14 heat changes in the gate, each will add 30 - 40 > minutes of delay as they fail and reset things behind them. So 7 - 10 > hours of gate delay for everyone because of these patches. > > Could heat team members get engaged and get to the bottom of this one?
I think this is the change we need to land to fix it: https://review.openstack.org/#/c/219533/ Can it be bumped to the head of the queue? Steve __________________________________________________________________________ OpenStack Development Mailing List (not for usage questions) Unsubscribe: [email protected]?subject:unsubscribe http://lists.openstack.org/cgi-bin/mailman/listinfo/openstack-dev