[email protected] wrote:

Hi everyone,

Two weeks ago, I received an information about changing affecting DB schema [1] from Henry Gessau just a day before the deadline. I was so surprised about this and could not change my plan for my patch sets. Do you know any plan for this ?
In the future, do you have plan for this in Netwon cycle?

[1] http://lists.openstack.org/pipermail/openstack-dev/2016-March/088680.html


I don’t see any issue with updating the patches you have for Newton. You have 6 months to get your patches in Newton. The alembic cut-off date for Newton will occur at the end of the current cycle.

Ihar

__________________________________________________________________________
OpenStack Development Mailing List (not for usage questions)
Unsubscribe: [email protected]?subject:unsubscribe
http://lists.openstack.org/cgi-bin/mailman/listinfo/openstack-dev