Steve Martinelli wrote:
A few keystone specific dates and definitions:
- May 30-03 -> R-18 -> **Spec proposal freeze**
- Specs must be available for review by this week
- keystone newton-1 will be released this week
- Jul 04-06 -> R-13 -> **Spec freeze**
- Specs must be merged by this week
- Jul 11-15 -> R-12 -> **Feature proposal freeze**
- Features must be available for review, passing Jenkins and not WIP
by this week
- keystone newton-2 will be released this week
- Aug 29-02 -> R-5 -> **Feature Freeze**
- Features must be merged by this week
- keystone newton-3 will be released this week
A few notes:
- The midcycle meetup will likely happen on R14, R12 or R11 [1]
- As always, folks can ask for a spec or feature exemption by explaining
their case on the mailing list
- The full schedule [2]
[1]
http://lists.openstack.org/pipermail/openstack-dev/2016-April/092298.html
[2] http://releases.openstack.org/newton/schedule.html
Feel free to propose an update to the Newton schedule to add those
Keystone-specific dates in ! The file to change is at:
http://git.openstack.org/cgit/openstack/releases/tree/doc/source/newton/schedule.rst
Cheers,
--
Thierry Carrez (ttx)
__________________________________________________________________________
OpenStack Development Mailing List (not for usage questions)
Unsubscribe: [email protected]?subject:unsubscribe
http://lists.openstack.org/cgi-bin/mailman/listinfo/openstack-dev