There are still a few design summit sessions from the summit that I'll recap but I wanted to get the priorities session recap out as early as possible. We held that session in the last slot on Thursday. The full etherpad is here [1].

The first part of the session was mostly going over schedule milestones.

We already started Newton with a freeze on spec approvals for new things since we already have a sizable backlog [2]. Now that we're past the summit we can approve specs for new things again.

The full Newton release schedule for Nova is in this wiki [3].

These are the major dates from here on out:

* June 2: newton-1, non-priority spec approval freeze
* June 30: non-priority feature freeze
* July 15: newton-2
* July 19-21: Nova Midcycle
* Aug 4: priority spec approval freeze
* Sept 2: newton-3, final python-novaclient release, FeatureFreeze, Soft StringFreeze
* Sept 16: RC1 and Hard StringFreeze
* Oct 7, 2016: Newton Release

The important thing for most people right now is we have exactly four weeks until the non-priority spec approval freeze. We then have about one month after that to land all non-priority blueprints.

Keep in mind that we've already got 52 approved blueprints and most of those were re-approved from Mitaka, so have been approved for several weeks already.

The non-priority blueprint cycle is intentionally restricted in Newton because of all of the backlog work we've had spilling over into this release. We really need to focus on getting as much of that done as possible before taking on more new work.

For the rest of the priorities session we talked about what our actual review priorities are for Newton. The list with details and owners is already available here [4].

In no particular order, these are the review priorities:

* Cells v2
* Scheduler
* API Improvements
* os-vif integration
* libvirt storage pools (for live migration)
* Get Me a Network
* Glance v2 Integration

We *should* be able to knock out glance v2, get-me-a-network and os-vif relatively soon (I'm thinking sometime in June).

Not listed in [4] but something we talked about was volume multi-attach with Cinder. We said this was going to be a 'stretch goal' contingent on making decent progress on that item by non-priority feature freeze *and* we get the above three smaller priority items completed.

Another thing we talked about but isn't going to be a priority is NFV-related work. We talked about cleaning up technical debt and additional testing for NFV but had no one in the session signed up to own that work or with concrete proposals on how to make improvements in that area. Since we can't assign review priorities to something that nebulous it was left out. Having said that, Moshe Levi has volunteered to restart and lead the SR-IOV/PCI bi-weekly meeting [5] (thanks again, Moshe!). So if you (or your employer, or your vendor) are interested in working on NFV in Nova please attend that meeting and get involved in helping out that subteam.

[1] https://etherpad.openstack.org/p/newton-nova-summit-priorities
[2] http://lists.openstack.org/pipermail/openstack-dev/2016-March/090370.html
[3] https://wiki.openstack.org/wiki/Nova/Newton_Release_Schedule
[4] https://specs.openstack.org/openstack/nova-specs/priorities/newton-priorities.html [5] http://lists.openstack.org/pipermail/openstack-dev/2016-April/093541.html

--

Thanks,

Matt Riedemann


__________________________________________________________________________
OpenStack Development Mailing List (not for usage questions)
Unsubscribe: openstack-dev-requ...@lists.openstack.org?subject:unsubscribe
http://lists.openstack.org/cgi-bin/mailman/listinfo/openstack-dev

Reply via email to