Hi,

On 07.12.2016 01:44, TN TN wrote:
> Hi, is there anyway to modify a target after its part of a task? Thanks, TN

as long as any task is referencing a target you can only modify the
name, comment or alive test of a target.

If you want to change any other option of a target (e.g. Hosts or port
list) you need to work with alterable tasks. When using such alterable
tasks you can change the task to another (dummy-)target, then modify the
original task and re-assign it back to your task.

Regards,

-- 

Christian Fischer | PGP Key: 0x54F3CE5B76C597AD
Greenbone Networks GmbH | http://greenbone.net
Neuer Graben 17, 49074 Osnabrück, Germany | AG Osnabrück, HR B 202460
Geschäftsführer: Lukas Grunwald, Dr. Jan-Oliver Wagner