On a previous project we used Quest's Shareplex to perform a similar migration with almost no downtime. The high-level steps were something like this:
- start shareplex capture - take hot backup of the original db - build the new db, version 8.1.x - restore the hot backup to the new db - upgrade the new db to 9.2.x - start applying captured DML to the new db - once the new db is near in-sync with the old db, shutdown the old db - apply remaining DML to new db (should take a few seconds/minutes) - switch over applications to point to the new db
Mike
Chindarkar, Chetan (CONS FIN , Contractor) wrote:
Kindly read the whole scenario and let me know your views.
(1) What we have ?
* Three db instances on the same machine. * Two of the instances are on 8.1.7.4 * One of the instance is on 8.1.6.0 * Oracle as well as O/S is running on 32-bit. * Database is running in archivelog mode. * The current box is Sun SPARK E6500. * Use BCV backup solutions with Veritas NetBackup for tape integration. * The production server (E6500) and the backup server both are physically located in Ohio. * The total db size is 1.5 TB.
(2) What we are going to do ?
* Migrate to a new E12K server. * Migrate all three instances to 9.2.0.4 * Install Oracle on top of 64-bit Sun Solaris 2.9 version. * Install 64-bit Oracle software on top of it. * The new server is supposed to be located in Arizona.
(3) How we are going to do ?
* Shut down all three instances on the production server. * Take the backup on the backup server. * Copy the data on to tape. * Ship the tapes over to Arizona where the new E12K box resides. * Copy all the data from tape on to the new E12K. * Upgrade all three instances on the new E12K as mentioned above on DAY1. * Back up all the data locally. * Now it takes around 2 days to ship all the tapes are shipped to Arizona and then copy the data over to new E12K. During this time the users are still accessing the production server in Mason. Also the etl jobs are updating/inserting/deleting data from this server in those two days.
(4) Whether this is possible ?
* Now lets say we want to apply just the changed data from DAY1 till DAY3 is there any way I can do it ? The only other option we have at this moment is to run all the jobs against the newly configured E12K. (I guess the answer is NO, but just wanted to confirm with u all)
----------------------------------------------------------------------------------------------------------------------
Thanks, Chetan
-- Please see the official ORACLE-L FAQ: http://www.orafaq.net -- Author: Mike Spalinger INET: [EMAIL PROTECTED]
Fat City Network Services -- 858-538-5051 http://www.fatcity.com San Diego, California -- Mailing list and web hosting services --------------------------------------------------------------------- To REMOVE yourself from this mailing list, send an E-Mail message to: [EMAIL PROTECTED] (note EXACT spelling of 'ListGuru') and in the message BODY, include a line containing: UNSUB ORACLE-L (or the name of mailing list you want to be removed from). You may also send the HELP command for other information (like subscribing).