OSP reports approximately 2000 feet of fiber has been ripped down from the 
poles a 144 count and a 48 count fiber. Construction crews and Splicers have 
been notified and are currently being dispatched to make repairs. No ETR at 
this time.

>> Confirmed affecting some of our Electric Lightwave services... Perhaps other 
>> carriers on this path as well.
>> “Remarks: There are live power lines on the ground with our damaged fibers. 
>> We have contacted Mid-State electric and they have given us an ETA of 
>> 10-11am. They will contact us when their crews are headed to the location.”

Peter Kranz
http://www.unwiredltd.com/
Desk: 510-868-1614 x100
Mobile: 510-207-0000
mailto:[email protected]

_______________________________________________
Outages mailing list
[email protected]
https://puck.nether.net/mailman/listinfo/outages

Reply via email to