You could add the scheduling fields to the Conchango scrum template, that is, the workitem types there you want to use for estimates. I've listed the types under Microsoft......Scheduling in this blog article http://geekswithblogs.net/terje/archive/2008/12/14/tfs-workitems--on-the-fields-their-namespaces-and-in.aspx . I've extracted the relevant table below:
Microsoft.VSTS.Scheduling namespace Name Used in CMMI Used in Agile Used in eScrum Used in VSTS Scrum RemainingWork Risk,Req,CR,Bug,Task Task Task Backlog,UserStory,Release CompletedWork Risk,Req,CR,Bug,Task Task Task Backlog,UserStory,Release BaselineWork Risk,Req,CR,Bug,Task Task PBI,Task Backlog,UserStory,Release StartDate Task Scenario,QoS,Task Backlog,UserStory,Release FinishDate Task Scenario,QoS,Task Backlog,UserStory,Release TaskHierarchy Task Task Task Backlog,UserStory,Release CR = Change Request, QoS = QualityOfService requirement, Req = Requirement The estimates goes into the Baseline field. Use the Process Editor to change the workitem types, add the fields (use the CMMI template workitemtypes as a base, copy the XML, that's the easiest way). If you use any special workitem tools, like for example Conchango Task Board, verify that that work for one workitemtype before you change them all. I'm not quite sure on that point. With the estimates filled in, and preferably also the Remaining Work you can both estimate, and follow up during the iteration/sprint/cycle. When you have the data filled in, you need a set of queries to extract the information you need, these should now be rather trivial. Since you won't have information down on day-level, just for a whole iteration (which is stored in the iteration path field), you'll need to do some programming in order to fill out a calendar control to be meaningful. _________________________ best regards Terje Sandstrøm Team System MVP http://www.osiris.no<http://www.osiris.no/> http://geekswithblogs.net/terje Mobile (+47) 95750354 From: [email protected] [mailto:[email protected]] On Behalf Of Grant Molloy Sent: 26. juni 2009 03:10 To: [email protected] Subject: Re: TFS Scheduling I don't think I explained what I was after too well... We want to be able to plan development cycles (or sprints in scrum terminology) for all members of the team, for whatever projects are coming up.. Simplistically, I would like a view of a month calendar control, showing dates blocked out because a sprint for whatever TFS project is planned for that period of time.. Would also like to be able to switch the view to show the scheduling of work per employee for the period of time. I don't want something that handles bugs, etc.. Just something simple that will allow our team to see what work is planned in the future, and who will be working on what. re: Sharepoint Portal... Unfortunately i'm not setup as an admin in this portal, so I'm not 100% aware of how it works from an Admin point of view.. On Fri, Jun 26, 2009 at 9:38 AM, Mitch Denny <[email protected]<mailto:[email protected]>> wrote: Not sure I follow. You can define multiple teams within the Process Template (via the SharePoint portal). Do you want to have a different sprint schedule per team? If that is the case it might make more sense to have two Team Projects??? From: [email protected]<mailto:[email protected]> [mailto:[email protected]<mailto:[email protected]>] On Behalf Of Grant Molloy Sent: Friday, 26 June 2009 9:19 AM To: [email protected]<mailto:[email protected]> Subject: TFS Scheduling Hi List, Just wondering whether there are any add-ons for TFS which allow a very simplistic scheduling of work?? We use the scrum methodology (or a modified version of it) to undertake our work, and we have the Scrum for Team System templates installed on our TFS install. However, the Scrum For Team System templates we have installed don't appear to provide anything to enable for scheduling of multiple sprints for the whole team, they seem to deal only with the Scrum process. -- Princess Margaret<http://www.brainyquote.com/quotes/authors/p/princess_margaret.html> - "I have as much privacy as a goldfish in a bowl." ________________________________ Support procedure: https://www.codify.com/lists/support List address: [email protected]<mailto:[email protected]> Subscribe: [email protected]<mailto:[email protected]> Unsubscribe: [email protected]<mailto:[email protected]> List FAQ: http://www.codify.com/lists/oztfs Other lists you might want to join: http://www.codify.com/lists ________________________________ Support procedure: https://www.codify.com/lists/support List address: [email protected]<mailto:[email protected]> Subscribe: [email protected]<mailto:[email protected]> Unsubscribe: [email protected]<mailto:[email protected]> List FAQ: http://www.codify.com/lists/oztfs Other lists you might want to join: http://www.codify.com/lists -- Yogi Berra<http://www.brainyquote.com/quotes/authors/y/yogi_berra.html> - "I never said most of the things I said." ________________________________ Support procedure: https://www.codify.com/lists/support List address: [email protected]<mailto:[email protected]> Subscribe: [email protected]<mailto:[email protected]> Unsubscribe: [email protected]<mailto:[email protected]> List FAQ: http://www.codify.com/lists/oztfs Other lists you might want to join: http://www.codify.com/lists -------------------------------------------------------------------------------- Support procedure: https://www.codify.com/lists/support List address: [email protected] Subscribe: [email protected] Unsubscribe: [email protected] List FAQ: http://www.codify.com/lists/oztfs Other lists you might want to join: http://www.codify.com/lists