On Wed, Mar 04, 2009 at 03:09:57PM -0800, Allison Randal wrote: > So, rather than adding "run the tests for X HLLs" to the release > process, I'd like to add "check with Y HLL project leads for any release > blockers" a couple of weeks in advance of the release. It puts the > testing burden back on the language developers, but also makes sure we > verify the languages before making the release. Sound workable?
I think a check needs to be done much closer to the release date than "a couple of weeks". Either that or we need to do some level of "code freeze" between the time of checking with project leads and the release. Otherwise we continue to have a good potential for the situation that gave rise to this issue in the first place. Pm _______________________________________________ http://lists.parrot.org/mailman/listinfo/parrot-dev
