On Mon, 2004-11-01 at 07:45, Mark Stosberg wrote:

> So, what resources are recommended to consult to make great estimates?
> What habits to develop?

I have two primary rules:

1) Don't make an estimate for something I haven't done before.
2) Don't make an estimate for anything that'll take longer than two or
three days.  If it's a much bigger project, break it into small,
estimable pieces, but don't go over a couple of weeks for estimates.

Could I give longer estimates?  Yes, but they will be rough guesses and
they won't be as accurate.

What happens when I need to estimate something I haven't done before?  I
take an afternoon to play with it to have some evidence for what the
real job will take.

-- c